Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,494
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0430 # 04 Y:2013 | 04 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $25,465 | $16,491 | Implemented |
SF0429 # 02 Y:2013 | 02 | 2013 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $578 | $810 | Implemented |
SF0429 # 05 Y:2013 | 05 | 2013 | USE COMPRESSOR AIR FILTERS | $9,736 | $36,817 | Implemented |
SF0429 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $919 | $5,601 | Implemented |
SF0428 # 01 Y:2013 | 01 | 2013 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $7,313 | $0 | Implemented |
SF0428 # 02 Y:2013 | 02 | 2013 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $5,121 | $0 | Implemented |
SF0428 # 04 Y:2013 | 04 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,736 | $1,751 | Implemented |
SF0428 # 07 Y:2013 | 07 | 2013 | INSULATE BARE EQUIPMENT | $1,669 | $1,332 | Implemented |
SF0428 # 10 Y:2013 | 10 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,972 | $12,679 | Implemented |
SF0426 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,979 | $17,191 | Implemented |
SF0425 # 01 Y:2013 | 01 | 2013 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $6,713 | $0 | Implemented |
SF0425 # 02 Y:2013 | 02 | 2013 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $15,421 | $7,471 | Implemented |
SF0425 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,808 | $7,235 | Implemented |
SF0425 # 07 Y:2013 | 07 | 2013 | INSTALL OCCUPANCY SENSORS | $3,416 | $13,849 | Implemented |
SF0425 # 08 Y:2013 | 08 | 2013 | HEAT WATER DURING OFF-PEAK PERIODS AND STORE FOR LATER USE | $692 | $2,830 | Implemented |
SF0424 # 01 Y:2013 | 01 | 2013 | INSTALL TIMERS AND/OR THERMOSTATS | $6,789 | $0 | Implemented |
SF0424 # 03 Y:2013 | 03 | 2013 | INCREASE AMOUNT OF CONDENSATE RETURNED | $10,307 | $0 | Implemented |
SF0424 # 06 Y:2013 | 06 | 2013 | INSTALL OCCUPANCY SENSORS | $7,962 | $46,705 | Implemented |
SF0424 # 07 Y:2013 | 07 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $79,423 | $291,716 | Implemented |
SF0423 # 01 Y:2012 | 01 | 2012 | CLOSE OFF UNNEEDED STEAM LINES | $417 | $0 | Implemented |
SF0423 # 02 Y:2012 | 02 | 2012 | REPAIR AND ELIMINATE STEAM LEAKS | $4,512 | $0 | Implemented |
SF0423 # 03 Y:2012 | 03 | 2012 | INSTALL SET-BACK TIMERS | $3,656 | $0 | Implemented |
SF0423 # 04 Y:2012 | 04 | 2012 | REPAIR OR REPLACE STEAM TRAPS | $5,375 | $3,925 | Implemented |
SF0423 # 06 Y:2012 | 06 | 2012 | INSULATE BARE EQUIPMENT | $4,091 | $4,108 | Implemented |
SF0423 # 07 Y:2012 | 07 | 2012 | INSTALL OCCUPANCY SENSORS | $14,919 | $21,094 | Implemented |