Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,202
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0611 # 02 Y:2024 | 02 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,908 | $0 | Implemented |
SF0611 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $61,975 | $1,800 | Implemented |
SF0611 # 04 Y:2024 | 04 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,353 | $2,100 | Not Implemented |
SF0611 # 05 Y:2024 | 05 | 2024 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $8,909 | $18,675 | Not Implemented |
SF0611 # 06 Y:2024 | 06 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $165,339 | $1,651,070 | Implemented |
SF0610 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,215 | $0 | Implemented |
SF0610 # 02 Y:2024 | 02 | 2024 | REPAIR AND ELIMINATE STEAM LEAKS | $12,954 | $0 | Implemented |
SF0610 # 03 Y:2024 | 03 | 2024 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $32,003 | $15,909 | Implemented |
SF0610 # 04 Y:2024 | 04 | 2024 | HEAT WATER WITH EXHAUST HEAT | $36,485 | $30,037 | Implemented |
SF0610 # 05 Y:2024 | 05 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $31,683 | $31,050 | Implemented |
SF0610 # 06 Y:2024 | 06 | 2024 | INSTALL OCCUPANCY SENSORS | $8,502 | $10,799 | Implemented |
SF0610 # 07 Y:2024 | 07 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $32,191 | $83,238 | Not Implemented |
SF0610 # 08 Y:2024 | 08 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $85,768 | $772,344 | Not Implemented |
SF0609 # 01 Y:2023 | 01 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $12,048 | $1,594 | Implemented |
SF0609 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,389 | $1,640 | Implemented |
SF0609 # 03 Y:2023 | 03 | 2023 | USE OPTIMUM THICKNESS INSULATION | $1,473 | $338 | Implemented |
SF0609 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,090 | $2,155 | Implemented |
SF0609 # 05 Y:2023 | 05 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $32,617 | $36,367 | Implemented |
SF0609 # 06 Y:2023 | 06 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $56,467 | $66,447 | Implemented |
SF0609 # 07 Y:2023 | 07 | 2023 | USE OPTIMUM THICKNESS INSULATION | $8,652 | $21,442 | Not Implemented |
SF0609 # 08 Y:2023 | 08 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,153 | $9,827 | Not Implemented |
SF0609 # 09 Y:2023 | 09 | 2023 | INSTALL WIND POWERED ELECTRIC GENERATOR | $426,217 | $1,338,900 | Not Implemented |
SF0608 # 01 Y:2023 | 01 | 2023 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $16,747 | $400 | Implemented |
SF0608 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,322 | $0 | Implemented |
SF0608 # 03 Y:2023 | 03 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $29,842 | $690 | Implemented |