Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
193
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SJ0025 # 10 Y:2024 | 10 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $11,258 | $0 | n/a |
SJ0025 # 03 Y:2024 | 03 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,130 | $16,703 | n/a |
SJ0025 # 09 Y:2024 | 09 | 2024 | INSTALL OCCUPANCY SENSORS | $182 | $160 | n/a |
SJ0025 # 06 Y:2024 | 06 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $31,290 | $0 | n/a |
SJ0025 # 07 Y:2024 | 07 | 2024 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $1,211 | $989 | n/a |
SJ0025 # 08 Y:2024 | 08 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $522 | $2,897 | n/a |
SJ0025 # 04 Y:2024 | 04 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $6,936 | $0 | n/a |
SJ0025 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $67,207 | $14,360 | n/a |
SJ0025 # 02 Y:2024 | 02 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $991 | $0 | n/a |
SJ0025 # 05 Y:2024 | 05 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $475 | $125 | n/a |
SJ0024 # 02 Y:2024 | 02 | 2024 | USE BATTERY STORAGE FOR DEMAND CONTROL | $3,606 | $5,559 | n/a |
SJ0024 # 03 Y:2024 | 03 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $490 | $0 | n/a |
SJ0024 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,292 | $8,243 | n/a |
SJ0024 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $45,462 | $42,170 | n/a |
SJ0024 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,182 | $0 | n/a |
SJ0024 # 06 Y:2024 | 06 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,248 | $0 | n/a |
SJ0023 # 07 Y:2024 | 07 | 2024 | INSULATE BARE EQUIPMENT | $190 | $380 | n/a |
SJ0023 # 05 Y:2024 | 05 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,164 | $1,874 | n/a |
SJ0023 # 03 Y:2024 | 03 | 2024 | INSTALL OCCUPANCY SENSORS | $1,478 | $305 | n/a |
SJ0023 # 02 Y:2024 | 02 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $848 | $2,144 | n/a |
SJ0023 # 06 Y:2024 | 06 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,625 | $0 | n/a |
SJ0023 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $21,134 | $146,494 | n/a |
SJ0023 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,823 | $2,466 | n/a |
SJ0022 # 05 Y:2024 | 05 | 2024 | REDUCE HEAT GAIN BY WINDOW TINTING | $367 | $2,139 | n/a |
SJ0022 # 03 Y:2024 | 03 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $213 | $179 | n/a |