IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

38

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SU0312 # 12 Y:2011 12 2011 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $276 $4,481 Implemented
SU0312 # 10 Y:2011 10 2011 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $474 $880 Implemented
SU0312 # 01 Y:2011 01 2011 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $6,080 $0 Implemented
SU0312 # 03 Y:2011 03 2011 DISCONNECT BALLASTS $1,584 $0 Implemented
SU0312 # 05 Y:2011 05 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $588 $283 Implemented
SU0312 # 07 Y:2011 07 2011 REDUCE VENTILATION AIR $13,505 $13,112 Implemented
SU0312 # 06 Y:2011 06 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $545 $175 Implemented
SU0311 # 03 Y:2011 03 2011 INSTALL OCCUPANCY SENSORS $2,682 $3,759 Implemented
SU0311 # 01 Y:2011 01 2011 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $379 $0 Implemented
SU0311 # 07 Y:2011 07 2011 OPTIMIZE PLANT POWER FACTOR $2,386 $21,091 Implemented
SU0311 # 02 Y:2011 02 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $12,621 $1,125 Implemented
SU0311 # 05 Y:2011 05 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $9,276 $19,890 Implemented
SU0309 # 08 Y:2011 08 2011 UPGRADE OBSOLETE EQUIPMENT $1,442 $16,500 Implemented
SU0309 # 07 Y:2011 07 2011 UPGRADE OBSOLETE EQUIPMENT $116 $1,258 Implemented
SU0309 # 05 Y:2011 05 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $68 $228 Implemented
SU0309 # 02 Y:2011 02 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $255 $147 Implemented
SU0309 # 01 Y:2011 01 2011 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $201 $0 Implemented
SU0308 # 02 Y:2011 02 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,204 $698 Implemented
SU0308 # 04 Y:2011 04 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,713 $625 Implemented
SU0307 # 05 Y:2011 05 2011 PREHEAT COMBUSTION AIR WITH WASTE HEAT $16,557 $21,257 Implemented
SU0307 # 06 Y:2011 06 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $9,579 $21,668 Implemented
SU0307 # 03 Y:2011 03 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $323 $97 Implemented
SU0307 # 01 Y:2011 01 2011 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,744 $0 Implemented
SU0306 # 05 Y:2011 05 2011 RECOVER AND REUSE COOLING WATER $32,137 $12,052 Implemented
SU0306 # 04 Y:2011 04 2011 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,901 $337 Implemented