Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,946
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0434 # 01 Y:1991 | 01 | 1991 | USE MINIMUM STEAM OPERATING PRESSURE | $1,745 | $2,550 | Implemented |
TN0434 # 02 Y:1991 | 02 | 1991 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,163 | $240 | Implemented |
TN0434 # 03 Y:1991 | 03 | 1991 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,504 | $3,650 | Implemented |
TN0434 # 04 Y:1991 | 04 | 1991 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $117 | $115 | Implemented |
TN0434 # 05 Y:1991 | 05 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $173 | $410 | Implemented |
TN0434 # 06 Y:1991 | 06 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $35 | $128 | Implemented |
TN0434 # 07 Y:1991 | 07 | 1991 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,785 | $0 | Implemented |
TN0442 # 01 Y:1991 | 01 | 1991 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $5,281 | $0 | Implemented |
TN0442 # 02 Y:1991 | 02 | 1991 | INSTALL TIMERS AND/OR THERMOSTATS | $4,589 | $1,330 | Implemented |
TN0442 # 03 Y:1991 | 03 | 1991 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,952 | $0 | Implemented |
TN0442 # 04 Y:1991 | 04 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,301 | $600 | Implemented |
TN0442 # 05 Y:1991 | 05 | 1991 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $12,142 | $0 | Implemented |
TN0439 # 01 Y:1991 | 01 | 1991 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $13,583 | $12,800 | Implemented |
TN0439 # 02 Y:1991 | 02 | 1991 | INSULATE BARE EQUIPMENT | $5,413 | $1,020 | Implemented |
TN0439 # 03 Y:1991 | 03 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,685 | $0 | Implemented |
TN0439 # 04 Y:1991 | 04 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,954 | $210 | Implemented |
TN0439 # 05 Y:1991 | 05 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,266 | $990 | Implemented |
TN0439 # 06 Y:1991 | 06 | 1991 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $352 | $0 | Implemented |
TN0444 # 01 Y:1991 | 01 | 1991 | USE RADIANT HEATER FOR SPOT HEATING | $1,613 | $3,410 | Implemented |
TN0444 # 02 Y:1991 | 02 | 1991 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,581 | $0 | Implemented |
TN0444 # 03 Y:1991 | 03 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $324 | $360 | Implemented |
TN0444 # 04 Y:1991 | 04 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $133 | $60 | Implemented |
TN0446 # 01 Y:1991 | 01 | 1991 | INSTALL TIMERS AND/OR THERMOSTATS | $5,675 | $2,700 | Implemented |
TN0446 # 02 Y:1991 | 02 | 1991 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,089 | $1,590 | Implemented |
TN0446 # 03 Y:1991 | 03 | 1991 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $507 | $0 | Implemented |