Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
42
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0694 # 11 Y:2000 | 11 | 2000 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,365 | $0 | Implemented |
TN0694 # 01 Y:2000 | 01 | 2000 | $219,860 | $100,000 | Not Implemented | |
TN0694 # 02 Y:2000 | 02 | 2000 | ADD AREA LIGHTING SWITCHES | $17,510 | $25,030 | Implemented |
TN0694 # 03 Y:2000 | 03 | 2000 | DEVELOP A REPAIR/REPLACE POLICY | $10,755 | $5,075 | Implemented |
TN0694 # 04 Y:2000 | 04 | 2000 | REDUCE AIR CONDITIONING LOAD BY EVAPORATING WATER FROM ROOF | $10,130 | $181,580 | Not Implemented |
TN0694 # 05 Y:2000 | 05 | 2000 | OPTIMIZE PLANT POWER FACTOR | $8,665 | $26,260 | Not Implemented |
TN0694 # 06 Y:2000 | 06 | 2000 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $6,210 | $18,900 | Not Implemented |
TN0694 # 07 Y:2000 | 07 | 2000 | USE FILTER AND DRYING OVEN TO REDUCE SLUDGE VOLUME | $4,345 | $9,100 | Not Implemented |
TN0694 # 08 Y:2000 | 08 | 2000 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $3,600 | $7,000 | Not Implemented |
TN0694 # 09 Y:2000 | 09 | 2000 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,795 | $1,875 | Not Implemented |
TN0694 # 10 Y:2000 | 10 | 2000 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $2,185 | $3,570 | Not Implemented |
TN0692 # 09 Y:2000 | 09 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,115 | $1,300 | Implemented |
TN0692 # 08 Y:2000 | 08 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,336 | $0 | Implemented |
TN0692 # 07 Y:2000 | 07 | 2000 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,600 | $900 | Implemented |
TN0692 # 06 Y:2000 | 06 | 2000 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,650 | $0 | Implemented |
TN0692 # 05 Y:2000 | 05 | 2000 | RECOVER AND REUSE WASTE MATERIAL | $4,210 | $0 | Implemented |
TN0692 # 04 Y:2000 | 04 | 2000 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $7,220 | $11,900 | Not Implemented |
TN0692 # 03 Y:2000 | 03 | 2000 | RECOVER WASTE HEAT FROM EQUIPMENT | $10,500 | $700 | Not Implemented |
TN0692 # 02 Y:2000 | 02 | 2000 | $899,000 | $967,000 | Implemented | |
TN0692 # 01 Y:2000 | 01 | 2000 | $3,613,000 | $645,000 | Not Implemented | |
TN0678 # 09 Y:2000 | 09 | 2000 | INSTALL / REPAIR INSULATION ON STEAM LINES | $277 | $0 | Implemented |
TN0678 # 08 Y:2000 | 08 | 2000 | REDUCE EXCESS STEAM BLEEDING | $350 | $170 | Implemented |
TN0678 # 07 Y:2000 | 07 | 2000 | ADD AREA LIGHTING SWITCHES | $1,320 | $2,660 | Not Implemented |
TN0678 # 06 Y:2000 | 06 | 2000 | MAKE A NEW BY-PRODUCT | $6,160 | $0 | Not Implemented |
TN0678 # 05 Y:2000 | 05 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,470 | $695 | Implemented |