Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
60
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UA0259 # 05 Y:2022 | 05 | 2022 | OPTIMIZE PLANT POWER FACTOR | $50,082 | $26,090 | Implemented |
UA0259 # 01 Y:2022 | 01 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $27,827 | $1,000 | Implemented |
UA0237 # 05 Y:2021 | 05 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $985 | $141 | Implemented |
UA0237 # 04 Y:2021 | 04 | 2021 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $12,431 | $551 | Implemented |
UA0237 # 03 Y:2021 | 03 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,989 | $50 | Implemented |
UA0237 # 02 Y:2021 | 02 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,075 | $9,020 | Implemented |
UA0237 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $46,741 | $78,276 | Implemented |
UA0214 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,674 | $35,762 | Implemented |
UA0214 # 09 Y:2019 | 09 | 2019 | PAY UTILITY BILLS ON TIME | $9,417 | $0 | Implemented |
UA0214 # 04 Y:2019 | 04 | 2019 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $48,099 | $7,241 | Implemented |
UA0214 # 07 Y:2019 | 07 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $57,024 | $7,375 | Implemented |
UA0214 # 05 Y:2019 | 05 | 2019 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $13,824 | $6,704 | Implemented |
UA0213 # 04 Y:2019 | 04 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,549 | $1,294 | Implemented |
UA0214 # 03 Y:2019 | 03 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $22,118 | $50 | Implemented |
UA0214 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,341 | $8,495 | Implemented |
UA0213 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,098 | $4,895 | Implemented |
UA0202 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $23,355 | $39,669 | Implemented |
UA0202 # 06 Y:2019 | 06 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,888 | $1,345 | Implemented |
UA0202 # 07 Y:2019 | 07 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $15,356 | $100 | Implemented |
UA0202 # 04 Y:2019 | 04 | 2019 | INSTALL TIMERS AND/OR THERMOSTATS | $29,377 | $15 | Implemented |
UA0202 # 02 Y:2019 | 02 | 2019 | INSTALL OCCUPANCY SENSORS | $4,359 | $17,407 | Implemented |
UA0181 # 02 Y:2017 | 02 | 2017 | INSTALL OCCUPANCY SENSORS | $5,103 | $11,746 | Implemented |
UA0181 # 04 Y:2017 | 04 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,999 | $2,465 | Implemented |
UA0181 # 05 Y:2017 | 05 | 2017 | INSTALL TIMERS AND/OR THERMOSTATS | $3,255 | $1,850 | Implemented |
UA0171 # 03 Y:2016 | 03 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,551 | $1,770 | Implemented |