IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,094

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UM0352 # 05 Y:2009 05 2009 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,200 $0 Implemented
UM0352 # 06 Y:2009 06 2009 RECOVER WASTE HEAT FROM EQUIPMENT $1,800 $1,900 Not Implemented
UM0352 # 07 Y:2009 07 2009 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,454 $0 Implemented
UM0352 # 08 Y:2009 08 2009 INSTALL OCCUPANCY SENSORS $504 $920 Implemented
UM0352 # 09 Y:2009 09 2009 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $3,944 $1,200 Implemented
UM0351 # 01 Y:2009 01 2009 TURN OFF EQUIPMENT WHEN NOT IN USE $37,050 $0 Implemented
UM0351 # 02 Y:2009 02 2009 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,706 $19,921 Implemented
UM0351 # 03 Y:2009 03 2009 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,516 $100 Not Implemented
UM0351 # 04 Y:2009 04 2009 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $2,124 $2,800 Not Implemented
UM0351 # 05 Y:2009 05 2009 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $1,656 $500 Implemented
UM0351 # 06 Y:2009 06 2009 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $1,506 $1,660 Not Implemented
UM0350 # 01 Y:2009 01 2009 RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING $14,346 $12,800 Not Implemented
UM0350 # 02 Y:2009 02 2009 RECOVER WASTE HEAT FROM EQUIPMENT $13,487 $13,000 Implemented
UM0350 # 03 Y:2009 03 2009 RECOVER WASTE HEAT FROM EQUIPMENT $7,300 $1,500 Not Implemented
UM0350 # 04 Y:2009 04 2009 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,744 $30,000 Implemented
UM0350 # 05 Y:2009 05 2009 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,990 $100 Not Implemented
UM0350 # 06 Y:2009 06 2009 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $8,186 $10,960 Not Implemented
UM0350 # 07 Y:2009 07 2009 INSULATE BARE EQUIPMENT $846 $474 Not Implemented
UM0350 # 08 Y:2009 08 2009 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $649 $1,200 Implemented
UM0349 # 01 Y:2009 01 2009 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $10,327 $1,000 Implemented
UM0349 # 02 Y:2009 02 2009 INSTALL OCCUPANCY SENSORS $5,172 $1,840 Implemented
UM0349 # 03 Y:2009 03 2009 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $3,531 $3,168 Implemented
UM0349 # 04 Y:2009 04 2009 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $479 $100 Implemented
UM0348 # 01 Y:2009 01 2009 TURN OFF EQUIPMENT WHEN NOT IN USE $56,000 $6,000 Implemented
UM0348 # 02 Y:2009 02 2009 TURN OFF EQUIPMENT WHEN NOT IN USE $51,000 $3,000 Implemented