Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
181
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0306 # 06 Y:2004 | 06 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,591 | $420 | Not Implemented |
WV0306 # 10 Y:2004 | 10 | 2004 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $796 | $40 | Implemented |
WV0306 # 12 Y:2004 | 12 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $696 | $3,480 | Implemented |
WV0306 # 07 Y:2004 | 07 | 2004 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,120 | $520 | Not Implemented |
WV0302 # 07 Y:2004 | 07 | 2004 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,889 | $80 | Implemented |
WV0302 # 02 Y:2004 | 02 | 2004 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $3,141 | $0 | Implemented |
WV0302 # 05 Y:2004 | 05 | 2004 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $3,067 | $7,050 | Not Implemented |
WV0302 # 06 Y:2004 | 06 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,066 | $2,200 | Implemented |
WV0302 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,072 | $7,735 | Implemented |
WV0302 # 11 Y:2004 | 11 | 2004 | DEVELOP A REPAIR/REPLACE POLICY | $731 | $300 | Implemented |
WV0302 # 09 Y:2004 | 09 | 2004 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $2,096 | $1,967 | Not Implemented |
WV0302 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,134 | $292 | Implemented |
WV0302 # 08 Y:2004 | 08 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,260 | $50 | Implemented |
WV0302 # 10 Y:2004 | 10 | 2004 | INSTALL OCCUPANCY SENSORS | $921 | $1,400 | Implemented |
WV0302 # 01 Y:2004 | 01 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,584 | $3,731 | Implemented |
WV0302 # 13 Y:2004 | 13 | 2004 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $5,450 | $5,000 | Implemented |
WV0302 # 12 Y:2004 | 12 | 2004 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $28,080 | $100 | Implemented |
WV0292 # 22 Y:2004 | 22 | 2004 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $8,249 | $1,200 | Implemented |
WV0292 # 25 Y:2004 | 25 | 2004 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $5,929 | $3,460 | Not Implemented |
WV0292 # 24 Y:2004 | 24 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,935 | $5,740 | Not Implemented |
WV0292 # 23 Y:2004 | 23 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,043 | $459 | Not Implemented |
WV0292 # 19 Y:2004 | 19 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $625 | $30 | Implemented |
WV0292 # 13 Y:2004 | 13 | 2004 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $3,626 | $750 | Implemented |
WV0292 # 12 Y:2004 | 12 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,851 | $528 | Implemented |
WV0292 # 01 Y:2004 | 01 | 2004 | INSULATE BARE EQUIPMENT | $27,182 | $23,577 | Implemented |