Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,265
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0360 # 02 Y:1999 | 02 | 1999 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,360 | $0 | Implemented |
AM0360 # 03 Y:1999 | 03 | 1999 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,140 | $0 | Implemented |
AM0360 # 04 Y:1999 | 04 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,100 | $500 | Implemented |
AM0360 # 05 Y:1999 | 05 | 1999 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,090 | $0 | Implemented |
AM0360 # 06 Y:1999 | 06 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $420 | $200 | Implemented |
AM0360 # 07 Y:1999 | 07 | 1999 | INSTALL OCCUPANCY SENSORS | $190 | $110 | Implemented |
AM0360 # 08 Y:1999 | 08 | 1999 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $100 | $0 | Implemented |
AM0359 # 01 Y:1999 | 01 | 1999 | INSULATE BARE EQUIPMENT | $7,930 | $1,340 | Implemented |
AM0359 # 02 Y:1999 | 02 | 1999 | SHIFT FROM DAYTIME TO NIGHTTIME OPERATION | $4,270 | $0 | Implemented |
AM0359 # 03 Y:1999 | 03 | 1999 | INSTALL EQUIPMENT TO MOVE PRODUCT | $3,430 | $100 | Implemented |
AM0359 # 06 Y:1999 | 06 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,350 | $560 | Implemented |
AM0359 # 08 Y:1999 | 08 | 1999 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $700 | $0 | Implemented |
AM0359 # 09 Y:1999 | 09 | 1999 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $340 | $26 | Implemented |
AM0359 # 10 Y:1999 | 10 | 1999 | PAY BILLS ON TIME TO AVOID LATE FEES | $235 | $0 | Implemented |
AM0359 # 11 Y:1999 | 11 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $220 | $90 | Implemented |
AM0358 # 01 Y:1999 | 01 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,480 | $1,500 | Implemented |
AM0358 # 02 Y:1999 | 02 | 1999 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,680 | $80 | Implemented |
AM0358 # 04 Y:1999 | 04 | 1999 | OPTIMIZE PLANT POWER FACTOR | $1,700 | $4,530 | Implemented |
AM0358 # 06 Y:1999 | 06 | 1999 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $115 | $110 | Implemented |
TP0008 # 01 Y:1999 | 01 | 1999 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $24,189 | $1,848 | Implemented |
AM0357 # 06 Y:1999 | 06 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $640 | $500 | Implemented |
AM0357 # 08 Y:1999 | 08 | 1999 | INSTALL OCCUPANCY SENSORS | $330 | $150 | Implemented |
AM0357 # 09 Y:1999 | 09 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $150 | $150 | Implemented |
AM0357 # 01 Y:1999 | 01 | 1999 | USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES | $250,000 | $285,000 | Implemented |
AM0357 # 03 Y:1999 | 03 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,500 | $30 | Implemented |