Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,763
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0579 # 06 Y:2022 | 06 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,095 | $12,753 | Implemented |
UF0579 # 08 Y:2022 | 08 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,003 | $0 | Implemented |
UF0579 # 10 Y:2022 | 10 | 2022 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $4,716 | $0 | Implemented |
UF0579 # 11 Y:2022 | 11 | 2022 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $540,144 | $53,000 | Implemented |
UF0578 # 01 Y:2022 | 01 | 2022 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $15,842 | $11,742 | Implemented |
UF0578 # 03 Y:2022 | 03 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,829 | $2,419 | Implemented |
UF0578 # 05 Y:2022 | 05 | 2022 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $7,688 | $0 | Implemented |
UF0578 # 06 Y:2022 | 06 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,461 | $390 | Implemented |
UF0578 # 07 Y:2022 | 07 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,930 | $0 | Implemented |
UF0578 # 08 Y:2022 | 08 | 2022 | INSTALL OCCUPANCY SENSORS | $1,065 | $1,710 | Implemented |
UF0577 # 01 Y:2022 | 01 | 2022 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $5,354 | $640 | Implemented |
UF0577 # 02 Y:2022 | 02 | 2022 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $3,407 | $2,618 | Implemented |
UF0577 # 03 Y:2022 | 03 | 2022 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $3,363 | $0 | Implemented |
UF0577 # 05 Y:2022 | 05 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,991 | $304 | Implemented |
UF0577 # 06 Y:2022 | 06 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,972 | $0 | Implemented |
UF0577 # 09 Y:2022 | 09 | 2022 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $1,049 | $200 | Implemented |
UF0577 # 10 Y:2022 | 10 | 2022 | SCHEDULE DELIVERIES ACCORDING TO DEMAND | $3,120 | $2,528 | Implemented |
UF0577 # 11 Y:2022 | 11 | 2022 | RECOVER AND REUSE WASTE MATERIAL | $28,657 | $31,000 | Implemented |
MI0405 # 01 Y:2022 | 01 | 2022 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $51,243 | $208,000 | Implemented |
MI0405 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $26,714 | $39,398 | Implemented |
MI0405 # 05 Y:2022 | 05 | 2022 | INSTALL OCCUPANCY SENSORS | $3,954 | $3,600 | Implemented |
UF0575 # 01 Y:2022 | 01 | 2022 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $320,724 | $1,068,750 | Implemented |
UF0575 # 03 Y:2022 | 03 | 2022 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $59,112 | $64,054 | Implemented |
UF0575 # 05 Y:2022 | 05 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,361 | $0 | Implemented |
UF0575 # 06 Y:2022 | 06 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,831 | $290 | Implemented |