Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
627
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0119 # 09 Y:2017 | 09 | 2017 | INSTALL OCCUPANCY SENSORS | $127 | $240 | Implemented |
UU0118 # 02 Y:2017 | 02 | 2017 | USE OPTIMUM TEMPERATURE | $7,381 | $0 | Implemented |
UU0117 # 01 Y:2017 | 01 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $57,965 | $96,413 | Implemented |
UU0117 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,843 | $1,647 | Implemented |
UU0116 # 01 Y:2017 | 01 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,863 | $0 | Implemented |
UU0116 # 05 Y:2017 | 05 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,534 | $2,402 | Implemented |
UU0116 # 06 Y:2017 | 06 | 2017 | INSTALL SPECTRAL REFLECTORS / DELAMP | $901 | $142 | Implemented |
UU0116 # 08 Y:2017 | 08 | 2017 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $59,018 | $500 | Implemented |
UU0115 # 01 Y:2017 | 01 | 2017 | DISCONNECT BALLASTS | $296 | $0 | Implemented |
UU0115 # 02 Y:2017 | 02 | 2017 | INSTALL OCCUPANCY SENSORS | $444 | $438 | Implemented |
UU0115 # 03 Y:2017 | 03 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,840 | $0 | Implemented |
UU0115 # 05 Y:2017 | 05 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $8,766 | $0 | Implemented |
UU0114 # 01 Y:2017 | 01 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,236 | $180 | Implemented |
UU0114 # 03 Y:2017 | 03 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $18,931 | $0 | Implemented |
UU0114 # 05 Y:2017 | 05 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,973 | $39,045 | Implemented |
UU0114 # 06 Y:2017 | 06 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,345 | $0 | Implemented |
BS0086 # 03 Y:2016 | 03 | 2016 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,887 | $280 | Implemented |
BS0086 # 04 Y:2016 | 04 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,877 | $1,280 | Implemented |
BS0076 # 02 Y:2016 | 02 | 2016 | UPGRADE CONTROLS ON COMPRESSORS | $5,025 | $2,777 | Implemented |
BS0076 # 03 Y:2016 | 03 | 2016 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,367 | $1,665 | Implemented |
BS0076 # 04 Y:2016 | 04 | 2016 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $962 | $14 | Implemented |
BS0076 # 05 Y:2016 | 05 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $737 | $871 | Implemented |
BS0076 # 06 Y:2016 | 06 | 2016 | INSULATE BARE EQUIPMENT | $655 | $768 | Implemented |
BS0076 # 07 Y:2016 | 07 | 2016 | TURN OFF EQUIPMENT WHEN NOT IN USE | $612 | $440 | Implemented |
BS0034 # 05 Y:2014 | 05 | 2014 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,083 | $304 | Implemented |