Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,486
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0097 # 05 Y:1994 | 05 | 1994 | INSTALL SPECTRAL REFLECTORS / DELAMP | $1,331 | $2,205 | Implemented |
SF0039 # 02 Y:1994 | 02 | 1994 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $10,590 | $2,750 | Implemented |
SF0039 # 03 Y:1994 | 03 | 1994 | INSULATE BARE EQUIPMENT | $2,733 | $3,713 | Implemented |
SF0039 # 04 Y:1994 | 04 | 1994 | INSTALL OCCUPANCY SENSORS | $2,811 | $2,400 | Implemented |
SF0039 # 05 Y:1994 | 05 | 1994 | ADD AREA LIGHTING SWITCHES | $1,444 | $130 | Implemented |
SF0039 # 07 Y:1994 | 07 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,811 | $2,759 | Implemented |
SF0038 # 01 Y:1994 | 01 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $843 | $600 | Implemented |
SF0038 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,673 | $4,082 | Implemented |
SF0038 # 03 Y:1994 | 03 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $147 | $141 | Implemented |
SD0096 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $29,182 | $22,260 | Implemented |
SD0096 # 05 Y:1994 | 05 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,631 | $11,471 | Implemented |
SF0037 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,919 | $2,799 | Implemented |
SF0037 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,817 | $1,277 | Implemented |
SF0037 # 04 Y:1994 | 04 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,271 | $900 | Implemented |
SF0037 # 05 Y:1994 | 05 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,048 | $1,189 | Implemented |
SF0037 # 06 Y:1994 | 06 | 1994 | INSULATE BARE EQUIPMENT | $225 | $190 | Implemented |
SF0037 # 07 Y:1994 | 07 | 1994 | REPAIR AND ELIMINATE STEAM LEAKS | $434 | $320 | Implemented |
SF0037 # 08 Y:1994 | 08 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,046 | $500 | Implemented |
SD0095 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,578 | $3,900 | Implemented |
SD0095 # 03 Y:1994 | 03 | 1994 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $474 | $1,400 | Implemented |
SD0095 # 04 Y:1994 | 04 | 1994 | INSULATE BARE EQUIPMENT | $582 | $750 | Implemented |
SD0095 # 05 Y:1994 | 05 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $157 | $720 | Implemented |
SD0095 # 06 Y:1994 | 06 | 1994 | INSTALL SPECTRAL REFLECTORS / DELAMP | $245 | $500 | Implemented |
SD0095 # 07 Y:1994 | 07 | 1994 | INSTALL OCCUPANCY SENSORS | $1,484 | $2,520 | Implemented |
SD0095 # 08 Y:1994 | 08 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $793 | $114 | Implemented |