Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,622
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0772 # 01 Y:2009 | 01 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,160 | $0 | Implemented |
OK0772 # 02 Y:2009 | 02 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,160 | $0 | Implemented |
OK0772 # 05 Y:2009 | 05 | 2009 | OPERATE BOILERS ON HIGH FIRE SETTING | $4,261 | $17,500 | Implemented |
OK0772 # 07 Y:2009 | 07 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,532 | $2,954 | Implemented |
OK0769 # 03 Y:2008 | 03 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $788 | $1,922 | Implemented |
OK0769 # 05 Y:2008 | 05 | 2008 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $21,911 | $4,475 | Implemented |
OK0766 # 01 Y:2008 | 01 | 2008 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $4,948 | $775 | Implemented |
OK0766 # 02 Y:2008 | 02 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,063 | $0 | Implemented |
OK0766 # 03 Y:2008 | 03 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $475 | $1,937 | Implemented |
OK0765 # 02 Y:2008 | 02 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $340 | $0 | Implemented |
OK0765 # 05 Y:2008 | 05 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,974 | $18,623 | Implemented |
OK0765 # 06 Y:2008 | 06 | 2008 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $42,105 | $161,000 | Implemented |
OK0762 # 01 Y:2008 | 01 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $164,842 | $297,920 | Implemented |
OK0762 # 02 Y:2008 | 02 | 2008 | INSTALL SKYLIGHTS | $14,224 | $54,912 | Implemented |
OK0762 # 05 Y:2008 | 05 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $31,605 | $1,000 | Implemented |
OK0762 # 06 Y:2008 | 06 | 2008 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $238,891 | $232,766 | Implemented |
OK0762 # 07 Y:2008 | 07 | 2008 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $17,165 | $0 | Implemented |
OK0761 # 01 Y:2008 | 01 | 2008 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,213 | $0 | Implemented |
OK0761 # 02 Y:2008 | 02 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $14,263 | $4,638 | Implemented |
OK0761 # 03 Y:2008 | 03 | 2008 | INSTALL OCCUPANCY SENSORS | $525 | $2,871 | Implemented |
OK0761 # 04 Y:2008 | 04 | 2008 | INSTALL SET-BACK TIMERS | $3,105 | $1,908 | Implemented |
OK0761 # 05 Y:2008 | 05 | 2008 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $5,200 | $0 | Implemented |
OK0760 # 01 Y:2008 | 01 | 2008 | $449,795 | $1,583,250 | Implemented | |
OK0760 # 02 Y:2008 | 02 | 2008 | $6,623 | $1,000 | Implemented | |
OK0760 # 03 Y:2008 | 03 | 2008 | $2,970 | $1,034 | Implemented |