Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,442
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0478 # 01 Y:2019 | 01 | 2019 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $25,716 | $2,242 | Implemented |
AS0477 # 05 Y:2019 | 05 | 2019 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,125 | $1,213 | Implemented |
AS0477 # 04 Y:2019 | 04 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,264 | $3,590 | Implemented |
AS0477 # 03 Y:2019 | 03 | 2019 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $17,100 | $7,907 | Implemented |
AS0477 # 02 Y:2019 | 02 | 2019 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $64,747 | $120,000 | Implemented |
AS0475 # 07 Y:2019 | 07 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $159 | $752 | Implemented |
AS0475 # 03 Y:2019 | 03 | 2019 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,779 | $895 | Implemented |
AS0475 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,094 | $5,938 | Implemented |
AS0474 # 08 Y:2019 | 08 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $77 | $0 | Implemented |
AS0474 # 05 Y:2019 | 05 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,935 | $516 | Implemented |
AS0474 # 04 Y:2019 | 04 | 2019 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,818 | $895 | Implemented |
AS0474 # 03 Y:2019 | 03 | 2019 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $7,733 | $750 | Implemented |
AS0474 # 02 Y:2019 | 02 | 2019 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $9,875 | $2,238 | Implemented |
AS0474 # 01 Y:2019 | 01 | 2019 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $20,118 | $5,404 | Implemented |
AS0473 # 07 Y:2019 | 07 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $699 | $1,891 | Implemented |
AS0473 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $647 | $2,803 | Implemented |
AS0473 # 03 Y:2019 | 03 | 2019 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $3,599 | $9,044 | Implemented |
AS0472 # 05 Y:2019 | 05 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,692 | $770 | Implemented |
AS0471 # 04 Y:2019 | 04 | 2019 | UPGRADE CONTROLS ON COMPRESSORS | $157 | $0 | Implemented |
AS0471 # 01 Y:2019 | 01 | 2019 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $85,359 | $279,692 | Implemented |
AS0470 # 01 Y:2019 | 01 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $680,774 | $3,152,400 | Implemented |
AS0470 # 05 Y:2019 | 05 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,823 | $3,204 | Implemented |
AS0470 # 02 Y:2019 | 02 | 2019 | UPGRADE CONTROLS ON COMPRESSORS | $19,947 | $40,400 | Implemented |
AS0470 # 03 Y:2019 | 03 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $19,843 | $10,895 | Implemented |
AS0470 # 04 Y:2019 | 04 | 2019 | REPAIR AND ELIMINATE STEAM LEAKS | $12,345 | $516 | Implemented |