Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
182
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TA0012 # 01 Y:2001 | 01 | 2001 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $14,730 | $0 | Implemented |
TA0012 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,435 | $0 | Implemented |
TA0011 # 01 Y:2001 | 01 | 2001 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $5,600 | $0 | Implemented |
TA0011 # 02 Y:2001 | 02 | 2001 | INSULATE BARE EQUIPMENT | $2,340 | $360 | Implemented |
TA0011 # 03 Y:2001 | 03 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,645 | $400 | Implemented |
TA0011 # 04 Y:2001 | 04 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $730 | $210 | Implemented |
TA0010 # 06 Y:2001 | 06 | 2001 | INSULATE FEEDWATER TANK | $2,564 | $181 | Implemented |
TA0010 # 01 Y:2001 | 01 | 2001 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $69,210 | $0 | Implemented |
TA0010 # 02 Y:2001 | 02 | 2001 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $29,986 | $11,995 | Implemented |
TA0010 # 03 Y:2001 | 03 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,834 | $40 | Implemented |
TA0010 # 04 Y:2001 | 04 | 2001 | PAY UTILITY BILLS ON TIME | $6,210 | $0 | Implemented |
TA0010 # 08 Y:2001 | 08 | 2001 | INSTALL OCCUPANCY SENSORS | $1,319 | $460 | Implemented |
TA0010 # 09 Y:2001 | 09 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $755 | $984 | Implemented |
TA0010 # 10 Y:2001 | 10 | 2001 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $520 | $0 | Implemented |
AM0402 # 11 Y:2001 | 11 | 2001 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $4,010 | $0 | Implemented |
AM0402 # 10 Y:2001 | 10 | 2001 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,325 | $0 | Implemented |
AM0402 # 01 Y:2001 | 01 | 2001 | REPAIR OR REPLACE STEAM TRAPS | $632,000 | $1,210 | Implemented |
AM0402 # 04 Y:2001 | 04 | 2001 | REPAIR AND ELIMINATE STEAM LEAKS | $27,400 | $1,000 | Implemented |
AM0402 # 06 Y:2001 | 06 | 2001 | INSULATE BARE EQUIPMENT | $19,300 | $865 | Implemented |
AM0402 # 09 Y:2001 | 09 | 2001 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $8,200 | $0 | Implemented |
TA0009 # 06 Y:2001 | 06 | 2001 | USE POWER DURING OFF-PEAK PERIODS | $210 | $0 | Implemented |
TA0009 # 05 Y:2001 | 05 | 2001 | TURN OFF EQUIPMENT WHEN NOT IN USE | $233 | $0 | Implemented |
TA0009 # 04 Y:2001 | 04 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $364 | $0 | Implemented |
TA0009 # 03 Y:2001 | 03 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,597 | $480 | Implemented |
TA0008 # 01 Y:2001 | 01 | 2001 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $18,300 | $0 | Implemented |