Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,245
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0556 # 01 Y:2020 | 01 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $33,420 | $174,290 | Implemented |
UF0555 # 05 Y:2020 | 05 | 2020 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $340,000 | $5,859 | Implemented |
UF0555 # 04 Y:2020 | 04 | 2020 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,821 | $3,900 | Implemented |
UF0555 # 03 Y:2020 | 03 | 2020 | INSTALL OCCUPANCY SENSORS | $2,700 | $10,047 | Implemented |
UF0555 # 02 Y:2020 | 02 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,846 | $7,217 | Implemented |
UF0555 # 01 Y:2020 | 01 | 2020 | INCREASE EFFICIENCY OF TRUCKS | $70,950 | $336,000 | Implemented |
MI0378 # 07 Y:2020 | 07 | 2020 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $1,694 | $1,195 | Implemented |
MI0378 # 06 Y:2020 | 06 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,909 | $1,980 | Implemented |
MI0378 # 05 Y:2020 | 05 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,502 | $2,100 | Implemented |
MI0378 # 04 Y:2020 | 04 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,737 | $11,160 | Implemented |
MI0378 # 01 Y:2020 | 01 | 2020 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $12,828 | $480 | Implemented |
MI0376 # 06 Y:2020 | 06 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,838 | $9,120 | Implemented |
UF0554 # 07 Y:2020 | 07 | 2020 | USE RE-USABLE FILTERS | $3,000 | $1,906 | Implemented |
UF0554 # 06 Y:2020 | 06 | 2020 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $30,206 | $6,500 | Implemented |
UF0554 # 05 Y:2020 | 05 | 2020 | INSTALL SENSORS TO DETECT DEFECTS | $3,851 | $15,420 | Implemented |
UF0554 # 04 Y:2020 | 04 | 2020 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $9,363 | $0 | Implemented |
UF0554 # 03 Y:2020 | 03 | 2020 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $6,420 | $17,086 | Implemented |
UF0554 # 02 Y:2020 | 02 | 2020 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $19,805 | $25,232 | Implemented |
UF0553 # 03 Y:2020 | 03 | 2020 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $1,490 | $5,608 | Implemented |
UF0553 # 02 Y:2020 | 02 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,460 | $28,443 | Implemented |
UF0553 # 05 Y:2020 | 05 | 2020 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $2,236 | $0 | Implemented |
UF0552 # 06 Y:2020 | 06 | 2020 | INSTALL AN UNINTERUPTABLE POWER SUPPLY | $45,577 | $65,793 | Implemented |
UF0552 # 05 Y:2020 | 05 | 2020 | INSTALL OCCUPANCY SENSORS | $2,364 | $6,394 | Implemented |
UF0552 # 04 Y:2020 | 04 | 2020 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $3,882 | $5,338 | Implemented |
UF0552 # 03 Y:2020 | 03 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,179 | $10,903 | Implemented |