Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,075
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0515 # 02 Y:1994 | 02 | 1994 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,074 | $1,300 | Implemented |
TN0515 # 03 Y:1994 | 03 | 1994 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,662 | $0 | Implemented |
TN0515 # 04 Y:1994 | 04 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,397 | $600 | Implemented |
TN0517 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,223 | $8,688 | Implemented |
TN0517 # 02 Y:1994 | 02 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,213 | $1,080 | Implemented |
TN0531 # 03 Y:1994 | 03 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,941 | $1,848 | Implemented |
TN0531 # 06 Y:1994 | 06 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $141 | $430 | Implemented |
TN0530 # 05 Y:1994 | 05 | 1994 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,015 | $0 | Implemented |
TN0530 # 10 Y:1994 | 10 | 1994 | MAKE A NEW BY-PRODUCT | $100,000 | $988,447 | Implemented |
TN0529 # 01 Y:1994 | 01 | 1994 | COVER OPEN TANKS | $8,253 | $100 | Implemented |
TN0529 # 02 Y:1994 | 02 | 1994 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $3,332 | $0 | Implemented |
TN0529 # 07 Y:1994 | 07 | 1994 | INSTALL SHROUDING ON MACHINES TO PREVENT SPLASHING | $7,800 | $344 | Implemented |
TN0529 # 09 Y:1994 | 09 | 1994 | IMPROVED MATERIAL HANDLING (MIXING AND TRANSFER) | $5,574 | $0 | Implemented |
TN0518 # 01 Y:1994 | 01 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,334 | $1,000 | Implemented |
TN0518 # 07 Y:1994 | 07 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,013 | $200 | Implemented |
TN0518 # 08 Y:1994 | 08 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $98 | $108 | Implemented |
TN0514 # 01 Y:1994 | 01 | 1994 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $28,698 | $23,000 | Implemented |
TN0514 # 02 Y:1994 | 02 | 1994 | INSULATE BARE EQUIPMENT | $6,641 | $2,168 | Implemented |
TN0514 # 03 Y:1994 | 03 | 1994 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,001 | $1,750 | Implemented |
TN0514 # 04 Y:1994 | 04 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $13,643 | $2,700 | Implemented |
TN0512 # 01 Y:1994 | 01 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,901 | $840 | Implemented |
TN0527 # 01 Y:1994 | 01 | 1994 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $9,612 | $5,000 | Implemented |
TN0527 # 02 Y:1994 | 02 | 1994 | INSULATE BARE EQUIPMENT | $4,817 | $3,055 | Implemented |
TN0527 # 03 Y:1994 | 03 | 1994 | REPAIR AND ELIMINATE STEAM LEAKS | $1,930 | $450 | Implemented |
TN0527 # 04 Y:1994 | 04 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,444 | $1,500 | Implemented |