Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,486
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0467 # 03 Y:2013 | 03 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,612 | $500 | Implemented |
SD0467 # 05 Y:2013 | 05 | 2013 | REPAIR AND ELIMINATE STEAM LEAKS | $2,867 | $200 | Implemented |
SD0467 # 06 Y:2013 | 06 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,309 | $200 | Implemented |
SD0467 # 08 Y:2013 | 08 | 2013 | USE PHOTOCELL CONTROLS | $1,846 | $2,628 | Implemented |
SF0430 # 01 Y:2013 | 01 | 2013 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $4,421 | $0 | Implemented |
SF0430 # 02 Y:2013 | 02 | 2013 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $1,697 | $768 | Implemented |
SF0430 # 03 Y:2013 | 03 | 2013 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $6,822 | $885 | Implemented |
SF0430 # 04 Y:2013 | 04 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $25,465 | $16,491 | Implemented |
SF0429 # 02 Y:2013 | 02 | 2013 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $578 | $810 | Implemented |
SF0429 # 05 Y:2013 | 05 | 2013 | USE COMPRESSOR AIR FILTERS | $9,736 | $36,817 | Implemented |
SF0429 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $919 | $5,601 | Implemented |
SD0465 # 03 Y:2013 | 03 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,054 | $2,000 | Implemented |
SD0465 # 04 Y:2013 | 04 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,677 | $200 | Implemented |
SD0464 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,895 | $27,250 | Implemented |
SF0428 # 01 Y:2013 | 01 | 2013 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $7,313 | $0 | Implemented |
SF0428 # 02 Y:2013 | 02 | 2013 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $5,121 | $0 | Implemented |
SF0428 # 04 Y:2013 | 04 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,736 | $1,751 | Implemented |
SF0428 # 07 Y:2013 | 07 | 2013 | INSULATE BARE EQUIPMENT | $1,669 | $1,332 | Implemented |
SF0428 # 10 Y:2013 | 10 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,972 | $12,679 | Implemented |
SD0463 # 04 Y:2013 | 04 | 2013 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $2,768 | $2,210 | Implemented |
SF0426 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,979 | $17,191 | Implemented |
SF0425 # 01 Y:2013 | 01 | 2013 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $6,713 | $0 | Implemented |
SF0425 # 02 Y:2013 | 02 | 2013 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $15,421 | $7,471 | Implemented |
SF0425 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,808 | $7,235 | Implemented |
SF0425 # 07 Y:2013 | 07 | 2013 | INSTALL OCCUPANCY SENSORS | $3,416 | $13,849 | Implemented |