Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
465
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0462 # 06 Y:2013 | 06 | 2013 | REPAIR OR REPLACE STEAM TRAPS | $42,971 | $6,850 | Implemented |
WV0462 # 07 Y:2013 | 07 | 2013 | INSTALL / REPAIR INSULATION ON STEAM LINES | $25,992 | $29,385 | Implemented |
WV0462 # 08 Y:2013 | 08 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,934 | $15,779 | Implemented |
WV0462 # 09 Y:2013 | 09 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,970 | $1,530 | Implemented |
WV0462 # 10 Y:2013 | 10 | 2013 | DEVELOP A REPAIR/REPLACE POLICY | $7,809 | $8,200 | Implemented |
WV0462 # 11 Y:2013 | 11 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,390 | $7,119 | Implemented |
WV0461 # 01 Y:2013 | 01 | 2013 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $166,335 | $175,000 | Implemented |
WV0461 # 03 Y:2013 | 03 | 2013 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $40,724 | $0 | Implemented |
WV0461 # 04 Y:2013 | 04 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $14,386 | $31,000 | Implemented |
WV0461 # 05 Y:2013 | 05 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,595 | $800 | Implemented |
DL0099 # 01 Y:2012 | 01 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,066 | $12,089 | Implemented |
DL0099 # 02 Y:2012 | 02 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,900 | $11,930 | Implemented |
DL0099 # 03 Y:2012 | 03 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,698 | $17,843 | Implemented |
DL0099 # 04 Y:2012 | 04 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,410 | $100 | Implemented |
DL0099 # 05 Y:2012 | 05 | 2012 | USE OPTIMUM TEMPERATURE | $2,940 | $100 | Implemented |
DL0096 # 01 Y:2012 | 01 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,429 | $30,095 | Implemented |
DL0096 # 02 Y:2012 | 02 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,176 | $8,000 | Implemented |
DL0096 # 03 Y:2012 | 03 | 2012 | KEEP EQUIPMENT CLEAN | $2,296 | $1,200 | Implemented |
DL0096 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,791 | $500 | Implemented |
WV0459 # 05 Y:2012 | 05 | 2012 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $10,943 | $1,000 | Implemented |
WV0459 # 06 Y:2012 | 06 | 2012 | DEVELOP A REPAIR/REPLACE POLICY | $10,718 | $2,889 | Implemented |
WV0459 # 07 Y:2012 | 07 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,273 | $90 | Implemented |
WV0459 # 08 Y:2012 | 08 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,895 | $0 | Implemented |
WV0459 # 09 Y:2012 | 09 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,834 | $701 | Implemented |
WV0459 # 11 Y:2012 | 11 | 2012 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $1,330 | $90 | Implemented |