Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
457
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0080 # 06 Y:2012 | 06 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,140 | $10,000 | Implemented |
DL0074 # 01 Y:2011 | 01 | 2011 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $6,390 | $2,000 | Implemented |
DL0074 # 02 Y:2011 | 02 | 2011 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $12,050 | $4,500 | Implemented |
DL0074 # 03 Y:2011 | 03 | 2011 | KEEP EQUIPMENT CLEAN | $9,770 | $2,000 | Implemented |
DL0074 # 07 Y:2011 | 07 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,320 | $1,900 | Implemented |
DL0074 # 10 Y:2011 | 10 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $510 | $1,300 | Implemented |
DL0066 # 01 Y:2011 | 01 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,960 | $1,035 | Implemented |
DL0066 # 03 Y:2011 | 03 | 2011 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $2,460 | $2,000 | Implemented |
DL0066 # 04 Y:2011 | 04 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,015 | $4,000 | Implemented |
WV0410 # 01 Y:2010 | 01 | 2010 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $92,924 | $0 | Implemented |
WV0410 # 03 Y:2010 | 03 | 2010 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,551 | $2,200 | Implemented |
WV0410 # 04 Y:2010 | 04 | 2010 | IMPROVE LUBRICATION PRACTICES | $1,907 | $618 | Implemented |
WV0410 # 06 Y:2010 | 06 | 2010 | INSTALL OCCUPANCY SENSORS | $1,273 | $210 | Implemented |
WV0410 # 08 Y:2010 | 08 | 2010 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,020 | $67 | Implemented |
WV0410 # 10 Y:2010 | 10 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $200 | $20 | Implemented |
DL0050 # 02 Y:2010 | 02 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,070 | $300 | Implemented |
DL0050 # 05 Y:2010 | 05 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,850 | $34,600 | Implemented |
WV0405 # 01 Y:2010 | 01 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,129 | $42,755 | Implemented |
WV0405 # 02 Y:2010 | 02 | 2010 | USE RADIANT HEATER FOR SPOT HEATING | $8,114 | $4,540 | Implemented |
WV0405 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,475 | $4,751 | Implemented |
WV0405 # 04 Y:2010 | 04 | 2010 | REDUCE VENTILATION AIR | $1,892 | $1,078 | Implemented |
WV0405 # 06 Y:2010 | 06 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,359 | $588 | Implemented |
WV0405 # 08 Y:2010 | 08 | 2010 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $747 | $1,000 | Implemented |
WV0405 # 10 Y:2010 | 10 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $367 | $27 | Implemented |
DL0051 # 01 Y:2010 | 01 | 2010 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,124 | $0 | Implemented |