Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,766
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0015 # 04 Y:1991 | 04 | 1991 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,364 | $8,000 | Implemented |
IA0015 # 07 Y:1991 | 07 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,300 | $4,278 | Implemented |
IA0015 # 01 Y:1991 | 01 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,595 | $0 | Implemented |
IA0015 # 06 Y:1991 | 06 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,851 | $100 | Implemented |
IA0015 # 02 Y:1991 | 02 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $846 | $1,980 | Implemented |
IA0015 # 03 Y:1991 | 03 | 1991 | INSTALL SET-BACK TIMERS | $440 | $200 | Implemented |
IA0015 # 05 Y:1991 | 05 | 1991 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,896 | $5,370 | Implemented |
AM0135 # 05 Y:1991 | 05 | 1991 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $630 | $340 | Implemented |
AS0043 # 04 Y:1991 | 04 | 1991 | INSTALL SET-BACK TIMERS | $818 | $1,575 | Implemented |
AS0044 # 06 Y:1991 | 06 | 1991 | INSTALL SET-BACK TIMERS | $1,172 | $1,050 | Implemented |
AS0044 # 08 Y:1991 | 08 | 1991 | IMPROVE LUBRICATION PRACTICES | $100 | $0 | Implemented |
AS0043 # 05 Y:1991 | 05 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $236 | $212 | Implemented |
AS0043 # 08 Y:1991 | 08 | 1991 | IMPROVE LUBRICATION PRACTICES | $124 | $0 | Implemented |
AS0043 # 07 Y:1991 | 07 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $124 | $100 | Implemented |
AM0135 # 02 Y:1991 | 02 | 1991 | INSULATE BARE EQUIPMENT | $2,190 | $100 | Implemented |
AS0044 # 01 Y:1991 | 01 | 1991 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $23,526 | $0 | Implemented |
AS0044 # 07 Y:1991 | 07 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $296 | $386 | Implemented |
WI0135 # 07 Y:1991 | 07 | 1991 | INSTALL TIMERS AND/OR THERMOSTATS | $321 | $400 | Implemented |
AM0135 # 04 Y:1991 | 04 | 1991 | RECOVER WASTE HEAT FROM EQUIPMENT | $840 | $1,009 | Implemented |
AM0135 # 03 Y:1991 | 03 | 1991 | INCREASE AMOUNT OF CONDENSATE RETURNED | $870 | $715 | Implemented |
AS0044 # 02 Y:1991 | 02 | 1991 | PLANT TREES OR SHRUBS NEAR WINDOWS TO SHIELD FROM SUNLIGHT | $1,984 | $7,500 | Implemented |
AM0135 # 07 Y:1991 | 07 | 1991 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $320 | $0 | Implemented |
AS0044 # 05 Y:1991 | 05 | 1991 | KEEP LAMPS AND REFLECTORS CLEAN | $9,959 | $3,003 | Implemented |
AS0044 # 04 Y:1991 | 04 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,142 | $12,130 | Implemented |
AS0043 # 06 Y:1991 | 06 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $572 | $830 | Implemented |