Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
352
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0108 # 01 Y:1983 | 01 | 1983 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $3,912 | $11,990 | Implemented |
OK0107 # 05 Y:1983 | 05 | 1983 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $2,813 | $2,000 | Implemented |
OK0107 # 04 Y:1983 | 04 | 1983 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $5,147 | $850 | Implemented |
OK0107 # 03 Y:1983 | 03 | 1983 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $4,270 | $2,875 | Implemented |
OK0107 # 02 Y:1983 | 02 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,222 | $34,425 | Implemented |
OK0107 # 01 Y:1983 | 01 | 1983 | OPTIMIZE PLANT POWER FACTOR | $1,492 | $5,215 | Implemented |
OK0103 # 04 Y:1983 | 04 | 1983 | INSTALL SET-BACK TIMERS | $153 | $333 | Implemented |
UD0105 # 04 Y:1983 | 04 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,661 | $167 | Implemented |
UD0106 # 03 Y:1983 | 03 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,363 | $2,153 | Implemented |
UD0106 # 01 Y:1983 | 01 | 1983 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $6,583 | $4,300 | Implemented |
UD0105 # 03 Y:1983 | 03 | 1983 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $3,286 | $3,840 | Implemented |
UD0104 # 06 Y:1983 | 06 | 1983 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $2,683 | $8,480 | Implemented |
UD0104 # 05 Y:1983 | 05 | 1983 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $1,680 | $3,100 | Implemented |
UD0104 # 04 Y:1983 | 04 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,605 | $1,592 | Implemented |
UD0104 # 03 Y:1983 | 03 | 1983 | INSTALL TIMERS AND/OR THERMOSTATS | $10,180 | $4,000 | Implemented |
UD0104 # 02 Y:1983 | 02 | 1983 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,527 | $0 | Implemented |
UD0104 # 01 Y:1983 | 01 | 1983 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $39,300 | $0 | Implemented |
UD0101 # 02 Y:1983 | 02 | 1983 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,217 | $0 | Implemented |
UD0100 # 04 Y:1983 | 04 | 1983 | INSTALL TIMERS AND/OR THERMOSTATS | $7,768 | $2,000 | Implemented |
UD0100 # 03 Y:1983 | 03 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,279 | $4,668 | Implemented |
UD0100 # 02 Y:1983 | 02 | 1983 | INSTALL STORM WINDOWS AND DOORS | $5,208 | $2,000 | Implemented |
UD0100 # 01 Y:1983 | 01 | 1983 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $3,030 | $1,000 | Implemented |
UD0095 # 04 Y:1983 | 04 | 1983 | INSTALL STORM WINDOWS AND DOORS | $3,398 | $2,560 | Implemented |
UD0095 # 03 Y:1983 | 03 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $583 | $172 | Implemented |
UD0095 # 01 Y:1983 | 01 | 1983 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $9,144 | $18,000 | Implemented |