Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,215
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0126 # 04 Y:1999 | 04 | 1999 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $1,825 | $25 | Implemented |
MS0126 # 05 Y:1999 | 05 | 1999 | $764 | $25 | Implemented | |
HO0191 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,167 | $5,870 | Implemented |
HO0191 # 02 Y:1999 | 02 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,826 | $120 | Implemented |
HO0191 # 04 Y:1999 | 04 | 1999 | REPLACE HIGH RESISTANCE DUCTS, PIPES, AND FITTINGS | $875 | $400 | Implemented |
HO0191 # 07 Y:1999 | 07 | 1999 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $1,125 | $500 | Implemented |
HO0191 # 08 Y:1999 | 08 | 1999 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $450 | $1,000 | Implemented |
AM0339 # 02 Y:1999 | 02 | 1999 | REPAIR AND ELIMINATE STEAM LEAKS | $2,575 | $1,500 | Implemented |
AM0339 # 05 Y:1999 | 05 | 1999 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $830 | $64 | Implemented |
AM0339 # 07 Y:1999 | 07 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $500 | $0 | Implemented |
AM0339 # 08 Y:1999 | 08 | 1999 | INSULATE BARE EQUIPMENT | $240 | $1,360 | Implemented |
AR0156 # 04 Y:1999 | 04 | 1999 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $82 | $0 | Implemented |
AR0156 # 05 Y:1999 | 05 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $564 | $170 | Implemented |
SF0157 # 01 Y:1999 | 01 | 1999 | INSTALL OCCUPANCY SENSORS | $1,834 | $1,456 | Implemented |
SF0157 # 02 Y:1999 | 02 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,418 | $45,400 | Implemented |
SF0157 # 03 Y:1999 | 03 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $396 | $2,106 | Implemented |
SF0157 # 05 Y:1999 | 05 | 1999 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $960 | $250 | Implemented |
MO0247 # 03 Y:1999 | 03 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,594 | $3,453 | Implemented |
MO0247 # 04 Y:1999 | 04 | 1999 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $327 | $0 | Implemented |
WI0337 # 03 Y:1999 | 03 | 1999 | $5,222 | $5,700 | Implemented | |
WI0337 # 07 Y:1999 | 07 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,551 | $0 | Implemented |
WI0337 # 08 Y:1999 | 08 | 1999 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $990 | $5,024 | Implemented |
WI0337 # 09 Y:1999 | 09 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $433 | $640 | Implemented |
ND0318 # 11 Y:1999 | 11 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $280 | $180 | Implemented |
UF0216 # 03 Y:1999 | 03 | 1999 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $6,211 | $0 | Implemented |