Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,837
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0467 # 08 Y:2015 | 08 | 2015 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $707 | $104 | Implemented |
BS0067 # 05 Y:2015 | 05 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $470 | $535 | Implemented |
BS0067 # 04 Y:2015 | 04 | 2015 | UPGRADE CONTROLS ON COMPRESSORS | $1,007 | $1,161 | Implemented |
BS0067 # 03 Y:2015 | 03 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $473 | $528 | Implemented |
BS0067 # 02 Y:2015 | 02 | 2015 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $762 | $77 | Implemented |
MI0288 # 11 Y:2015 | 11 | 2015 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,333 | $80 | Implemented |
MI0288 # 10 Y:2015 | 10 | 2015 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,706 | $1,300 | Implemented |
MI0288 # 06 Y:2015 | 06 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,388 | $40 | Implemented |
MI0288 # 04 Y:2015 | 04 | 2015 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $9,840 | $4,691 | Implemented |
MI0288 # 02 Y:2015 | 02 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $19,212 | $1,670 | Implemented |
MI0288 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,939 | $91,936 | Implemented |
MZ0206 # 04 Y:2015 | 04 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $376 | $0 | Implemented |
MZ0206 # 03 Y:2015 | 03 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,082 | $2,600 | Implemented |
MZ0206 # 02 Y:2015 | 02 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,931 | $890 | Implemented |
UD0938 # 07 Y:2015 | 07 | 2015 | DEVELOP A REPAIR/REPLACE POLICY | $152 | $530 | Implemented |
UD0938 # 06 Y:2015 | 06 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,415 | $0 | Implemented |
UD0938 # 02 Y:2015 | 02 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,298 | $0 | Implemented |
UA0151 # 01 Y:2015 | 01 | 2015 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $107,877 | $42,000 | Implemented |
UA0151 # 02 Y:2015 | 02 | 2015 | INCREASE AMOUNT OF CONDENSATE RETURNED | $48,953 | $110,000 | Implemented |
IP0053 # 01 Y:2015 | 01 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $57,305 | $915 | Implemented |
IP0053 # 02 Y:2015 | 02 | 2015 | INSTALL OCCUPANCY SENSORS | $1,294 | $160 | Implemented |
IP0053 # 03 Y:2015 | 03 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $38,029 | $5,000 | Implemented |
IP0053 # 04 Y:2015 | 04 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,650 | $2,685 | Implemented |
IP0053 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $456 | $924 | Implemented |
IP0052 # 07 Y:2015 | 07 | 2015 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $10,505 | $7,153 | Implemented |