IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,708

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WV0238 # 07 Y:2002 07 2002 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $649 $450 Implemented
WV0238 # 08 Y:2002 08 2002 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $4,813 $0 Implemented
WV0238 # 09 Y:2002 09 2002 USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER $6,165 $0 Not Implemented
WV0238 # 10 Y:2002 10 2002 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY $1,562 $150 Implemented
WV0238 # 11 Y:2002 11 2002 SELL / OFFER BY-PRODUCT AS ANIMAL FEED $2,080 $100 Implemented
WV0238 # 12 Y:2002 12 2002 CONTRACT A WOOD PALLET RECYCLING COMPANY $1,560 $100 Implemented
WV0238 # 13 Y:2002 13 2002 USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES $11,520 $1,620 Not Implemented
UD0646 # 01 Y:2002 01 2002 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE $33,646 $32,000 Implemented
UD0646 # 02 Y:2002 02 2002 INSTALL / REPAIR INSULATION ON STEAM LINES $25,468 $12,700 Implemented
UD0646 # 03 Y:2002 03 2002 USE DIRECT AIR SUPPLY TO EXHAUST HOODS $9,581 $675 Not Implemented
UD0646 # 04 Y:2002 04 2002 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $2,685 $2,000 Implemented
UD0646 # 05 Y:2002 05 2002 INSULATE BARE EQUIPMENT $2,204 $3,320 Not Implemented
UD0646 # 06 Y:2002 06 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,390 $5,088 Not Implemented
UD0646 # 07 Y:2002 07 2002 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,342 $61 Not Implemented
UD0646 # 08 Y:2002 08 2002 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $1,092 $0 Not Implemented
UD0646 # 09 Y:2002 09 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $613 $1,431 Not Implemented
UD0646 # 10 Y:2002 10 2002 INSTALL SPECTRAL REFLECTORS / DELAMP $379 $499 Implemented
UD0646 # 11 Y:2002 11 2002 CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS $311 $640 Not Implemented
AM0419 # 01 Y:2002 01 2002 INSTALL AN UNINTERUPTABLE POWER SUPPLY $180,000 $700,000 Not Implemented
AM0419 # 02 Y:2002 02 2002 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $14,460 $1,470 Implemented
AM0419 # 03 Y:2002 03 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,250 $2,000 Implemented
AM0419 # 04 Y:2002 04 2002 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $6,140 $1,140 Implemented
AM0419 # 05 Y:2002 05 2002 INSULATE BARE EQUIPMENT $3,970 $3,000 Not Implemented
AM0419 # 06 Y:2002 06 2002 USE SYNTHETIC LUBRICANT $3,415 $0 Not Implemented
AM0419 # 07 Y:2002 07 2002 USE PHOTOCELL CONTROLS $555 $200 Implemented