IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,314

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AS0205 # 06 Y:1997 06 1997 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $714 $40 Implemented
AS0205 # 07 Y:1997 07 1997 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,901 $70 Not Implemented
AS0205 # 08 Y:1997 08 1997 INSTALL OCCUPANCY SENSORS $1,348 $1,425 Not Implemented
AS0205 # 09 Y:1997 09 1997 TREAT AND REUSE RINSE WATERS $4,004 $950 Not Implemented
AS0205 # 10 Y:1997 10 1997 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $15,110 $4,500 Not Implemented
AS0205 # 11 Y:1997 11 1997 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL $2,076 $30 Implemented
AS0206 # 01 Y:1997 01 1997 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $10,800 $7,000 Not Implemented
AS0206 # 02 Y:1997 02 1997 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,330 $220 Implemented
AS0206 # 03 Y:1997 03 1997 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,393 $2,503 Not Implemented
AS0206 # 04 Y:1997 04 1997 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,124 $225 Not Implemented
AS0206 # 05 Y:1997 05 1997 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $377 $60 Implemented
AS0206 # 06 Y:1997 06 1997 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL $2,352 $30 Implemented
AS0206 # 07 Y:1997 07 1997 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL $1,760 $0 Not Implemented
AS0206 # 08 Y:1997 08 1997 DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS $12,000 $100 Not Implemented
AS0204 # 01 Y:1997 01 1997 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION $63,320 $2,400 Not Implemented
AS0204 # 02 Y:1997 02 1997 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $8,248 $16,974 Not Implemented
AS0204 # 03 Y:1997 03 1997 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $6,113 $8,000 Not Implemented
AS0204 # 04 Y:1997 04 1997 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,786 $60 Not Implemented
AS0204 # 05 Y:1997 05 1997 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,579 $0 Not Implemented
AS0204 # 06 Y:1997 06 1997 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,288 $3,115 Not Implemented
AS0204 # 07 Y:1997 07 1997 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,188 $1,381 Not Implemented
AS0204 # 08 Y:1997 08 1997 INSTALL OCCUPANCY SENSORS $696 $1,650 Not Implemented
AS0204 # 09 Y:1997 09 1997 INSTALL TIMERS AND/OR THERMOSTATS $324 $320 Not Implemented
AS0204 # 10 Y:1997 10 1997 USE EVAPORATION TO CONCENTRATE MATERIAL $36,527 $13,260 Not Implemented
AS0204 # 11 Y:1997 11 1997 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $56,857 $66,040 Not Implemented