Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
12,007
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0473 # 03 Y:2015 | 03 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,523 | $66 | Not Implemented |
SF0473 # 04 Y:2015 | 04 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $951 | $144 | Implemented |
SF0473 # 05 Y:2015 | 05 | 2015 | INSTALL OCCUPANCY SENSORS | $3,208 | $2,648 | Not Implemented |
SF0473 # 06 Y:2015 | 06 | 2015 | UPGRADE CONTROLS ON COMPRESSORS | $10,962 | $10,585 | Implemented |
SF0473 # 07 Y:2015 | 07 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,885 | $76,232 | Implemented |
SF0473 # 08 Y:2015 | 08 | 2015 | USE SOLAR HEAT TO MAKE ELECTRICTY | $121,903 | $1,110,964 | Implemented |
SF0473 # 09 Y:2015 | 09 | 2015 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $677 | $0 | Implemented |
SD0515 # 01 Y:2015 | 01 | 2015 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $209,960 | $1,040,000 | Not Implemented |
SD0515 # 02 Y:2015 | 02 | 2015 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $163,675 | $32,788 | Not Implemented |
SD0515 # 03 Y:2015 | 03 | 2015 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $49,380 | $151,600 | Not Implemented |
SD0515 # 04 Y:2015 | 04 | 2015 | UPGRADE OBSOLETE EQUIPMENT | $9,105 | $25,000 | Not Implemented |
SD0515 # 05 Y:2015 | 05 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $5,959 | $12,000 | Not Implemented |
SD0515 # 06 Y:2015 | 06 | 2015 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,564 | $5,290 | Not Implemented |
SD0515 # 07 Y:2015 | 07 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,240 | $1,550 | Not Implemented |
SD0515 # 08 Y:2015 | 08 | 2015 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $948 | $3,375 | Not Implemented |
SD0515 # 09 Y:2015 | 09 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $931 | $3,050 | Not Implemented |
SD0517 # 01 Y:2015 | 01 | 2015 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $69,718 | $163,200 | Implemented |
SD0517 # 02 Y:2015 | 02 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $54,474 | $5,633 | Not Implemented |
SD0517 # 03 Y:2015 | 03 | 2015 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $54,235 | $108,000 | Not Implemented |
SD0517 # 04 Y:2015 | 04 | 2015 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $18,457 | $11,700 | Implemented |
SD0517 # 05 Y:2015 | 05 | 2015 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $5,974 | $8,760 | Not Implemented |
SD0517 # 06 Y:2015 | 06 | 2015 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $3,975 | $9,935 | Not Implemented |
SD0517 # 07 Y:2015 | 07 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,154 | $2,000 | Implemented |
SD0517 # 08 Y:2015 | 08 | 2015 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $736 | $2,350 | Not Implemented |
SF0472 # 01 Y:2015 | 01 | 2015 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,587 | $527 | Implemented |