Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,315
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0111 # 06 Y:1995 | 06 | 1995 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $11,610 | $1,200 | Not Implemented |
IA0111 # 07 Y:1995 | 07 | 1995 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $2,022 | $1,716 | Not Implemented |
IA0111 # 08 Y:1995 | 08 | 1995 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $1,672 | $8,000 | Implemented |
IA0110 # 01 Y:1995 | 01 | 1995 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,304 | $79,400 | Implemented |
IA0110 # 02 Y:1995 | 02 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $12,241 | $1,577 | Implemented |
IA0110 # 03 Y:1995 | 03 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,217 | $1,816 | Not Implemented |
IA0110 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,911 | $520 | Not Implemented |
IA0110 # 05 Y:1995 | 05 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,877 | $8,050 | Not Implemented |
IA0110 # 06 Y:1995 | 06 | 1995 | INSTALL OCCUPANCY SENSORS | $203 | $539 | Not Implemented |
IA0110 # 07 Y:1995 | 07 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $144 | $270 | Implemented |
IA0108 # 01 Y:1995 | 01 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,025 | $240 | Not Implemented |
IA0108 # 02 Y:1995 | 02 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,336 | $860 | Implemented |
IA0108 # 03 Y:1995 | 03 | 1995 | INSTALL OCCUPANCY SENSORS | $442 | $770 | Implemented |
IA0108 # 04 Y:1995 | 04 | 1995 | INSULATE BARE EQUIPMENT | $622 | $142 | Not Implemented |
IA0108 # 05 Y:1995 | 05 | 1995 | INSULATE BARE EQUIPMENT | $427 | $1,142 | Implemented |
IA0108 # 06 Y:1995 | 06 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $513 | $200 | Implemented |
IA0108 # 07 Y:1995 | 07 | 1995 | REPLACE HEXAVALENT CHROMIUM SOLUTIONS WITH TRIVALENT SOLUTIONS | $3,023 | $0 | Not Implemented |
IA0108 # 08 Y:1995 | 08 | 1995 | USE SQUEEGEES, MOPS, AND VACUUMS FOR FLOOR CLEANING | $589 | $400 | Implemented |
IA0107 # 01 Y:1995 | 01 | 1995 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $4,944 | $300 | Implemented |
IA0107 # 02 Y:1995 | 02 | 1995 | INSTALL OCCUPANCY SENSORS | $1,738 | $2,999 | Not Implemented |
IA0107 # 03 Y:1995 | 03 | 1995 | PAY UTILITY BILLS ON TIME | $3,539 | $0 | Implemented |
IA0107 # 04 Y:1995 | 04 | 1995 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $2,231 | $1,843 | Implemented |
IA0107 # 05 Y:1995 | 05 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,094 | $20 | Not Implemented |
IA0107 # 06 Y:1995 | 06 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $525 | $149 | Implemented |
IA0106 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,241 | $554 | Implemented |