Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,289
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0230 # 04 Y:2002 | 04 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,301 | $2,500 | Not Implemented |
NC0230 # 05 Y:2002 | 05 | 2002 | ADD AREA LIGHTING SWITCHES | $1,053 | $3,340 | Implemented |
NC0230 # 06 Y:2002 | 06 | 2002 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $797 | $1,040 | Implemented |
NC0230 # 07 Y:2002 | 07 | 2002 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $645 | $1,100 | Not Implemented |
NC0230 # 08 Y:2002 | 08 | 2002 | USE RADIANT HEATER FOR SPOT HEATING | $263 | $0 | Not Implemented |
NC0230 # 09 Y:2002 | 09 | 2002 | LIMIT AND CONTROL SECONDARY COMBUSTION AIR IN FURNACE | $4,254 | $3,500 | Implemented |
NC0228 # 01 Y:2002 | 01 | 2002 | $296,000 | $75,000 | n/a | |
NC0228 # 02 Y:2002 | 02 | 2002 | USE COMPRESSOR AIR FILTERS | $41,667 | $10,600 | n/a |
NC0228 # 03 Y:2002 | 03 | 2002 | INTERLOCK HEATING AND AIR CONDITIONING SYSTEMS TO PREVENT SIMULTANEOUS OPERATION | $173,756 | $88,000 | n/a |
NC0228 # 04 Y:2002 | 04 | 2002 | REDESIGN PROCESS | $74,974 | $100,000 | n/a |
NC0228 # 05 Y:2002 | 05 | 2002 | UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS | $12,426 | $39,808 | n/a |
GT0724 # 01 Y:2001 | 01 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,810 | $8,370 | n/a |
GT0724 # 02 Y:2001 | 02 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,554 | $0 | Not Implemented |
GT0724 # 03 Y:2001 | 03 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,832 | $1,800 | Implemented |
GT0724 # 04 Y:2001 | 04 | 2001 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $4,279 | $5,900 | Implemented |
GT0724 # 05 Y:2001 | 05 | 2001 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $6,956 | $7,500 | Implemented |
GT0724 # 06 Y:2001 | 06 | 2001 | USE OPTIMUM TEMPERATURE | $45,009 | $3,850 | Not Implemented |
GT0723 # 01 Y:2001 | 01 | 2001 | DE-ENERGIZE EXCESS TRANSFORMER CAPACITY | $21,103 | $60,000 | Implemented |
GT0723 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $35,140 | $68,913 | Implemented |
GT0723 # 03 Y:2001 | 03 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,660 | $825 | Implemented |
GT0723 # 04 Y:2001 | 04 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,036 | $350 | Implemented |
GT0723 # 05 Y:2001 | 05 | 2001 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $76,655 | $0 | Implemented |
GT0723 # 06 Y:2001 | 06 | 2001 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,965 | $1,418 | Implemented |
NC0226 # 01 Y:2001 | 01 | 2001 | DEVELOP A REPAIR/REPLACE POLICY | $10,828 | $12,834 | Not Implemented |
NC0226 # 02 Y:2001 | 02 | 2001 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $3,348 | $500 | Not Implemented |