IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

5,105

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0671 # 06 Y:2003 06 2003 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $3,103 $442 Not Implemented
UD0671 # 07 Y:2003 07 2003 INSTALL OCCUPANCY SENSORS $896 $270 Not Implemented
UD0671 # 08 Y:2003 08 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $249 $702 Not Implemented
UM0234 # 01 Y:2003 01 2003 RECOVER WASTE HEAT FROM EQUIPMENT $71,900 $180,000 Implemented
UM0234 # 02 Y:2003 02 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $27,488 $360 Not Implemented
UM0234 # 03 Y:2003 03 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,415 $2,925 Not Implemented
UM0234 # 04 Y:2003 04 2003 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $10,603 $120,000 Implemented
UM0234 # 05 Y:2003 05 2003 COVER OPEN TANKS $8,523 $2,000 Not Implemented
UM0234 # 06 Y:2003 06 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,198 $5,219 Not Implemented
IA0317 # 01 Y:2003 01 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,624 $90 Implemented
IA0317 # 02 Y:2003 02 2003 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,056 $155 Implemented
IA0317 # 03 Y:2003 03 2003 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $435 $15 Implemented
IA0317 # 04 Y:2003 04 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,189 $6,998 Implemented
IA0317 # 05 Y:2003 05 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $930 $408 Implemented
IA0317 # 06 Y:2003 06 2003 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,527 $1,007 Implemented
IA0317 # 07 Y:2003 07 2003 CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS $8,984 $75,000 Implemented
IA0317 # 08 Y:2003 08 2003 AUTOMATE PAYROLL SYSTEM $15,600 $18,500 Not Implemented
MI0058 # 01 Y:2003 01 2003 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $11,548 $2,000 Not Implemented
MI0058 # 02 Y:2003 02 2003 REPAIR OR REPLACE STEAM TRAPS $1,906 $696 Implemented
MI0058 # 03 Y:2003 03 2003 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,543 $223 Not Implemented
MI0058 # 04 Y:2003 04 2003 METER WASTE WATER $12,786 $1,950 Not Implemented
MI0058 # 05 Y:2003 05 2003 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $250,000 $43,000 Implemented
MI0058 # 06 Y:2003 06 2003 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $13,520 $400,000 Implemented
SD0324 # 01 Y:2003 01 2003 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $18,616 $22,450 Not Implemented
SD0324 # 02 Y:2003 02 2003 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $13,814 $6,400 Not Implemented