IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,204

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MA0601 # 05 Y:2006 05 2006 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $5,090 $2,300 Not Implemented
WI0513 # 01 Y:2006 01 2006 IMPROVE SPACE COMFORT CONDITIONING $42,840 $1,800 Implemented
WI0513 # 02 Y:2006 02 2006 IMPROVE SPACE COMFORT CONDITIONING $16,286 $2,450 Not Implemented
WI0513 # 03 Y:2006 03 2006 RECOVER WASTE HEAT FROM EQUIPMENT $10,175 $1,000 Not Implemented
WI0513 # 04 Y:2006 04 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,710 $5,940 Implemented
WI0513 # 05 Y:2006 05 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,821 $640 Not Implemented
WI0513 # 06 Y:2006 06 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,987 $450 Not Implemented
WI0513 # 07 Y:2006 07 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,529 $0 Implemented
WI0513 # 08 Y:2006 08 2006 INSTALL TIMERS AND/OR THERMOSTATS $1,291 $400 Implemented
WI0513 # 09 Y:2006 09 2006 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,277 $200 Implemented
IC0114 # 01 Y:2006 01 2006 INSTALL TURBULATORS $42,000 $7,500 Not Implemented
IC0114 # 02 Y:2006 02 2006 CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS $16,000 $84,000 Not Implemented
IC0114 # 03 Y:2006 03 2006 MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT $19,000 $63,000 Implemented
IC0114 # 04 Y:2006 04 2006 CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS $175,000 $120,400 Not Implemented
IC0114 # 05 Y:2006 05 2006 RECOVER WASTE HEAT FROM EQUIPMENT $8,400 $16,800 Not Implemented
IC0114 # 06 Y:2006 06 2006 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $4,216 $5,280 Not Implemented
IC0114 # 07 Y:2006 07 2006 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR $93,057 $456,000 Not Implemented
IC0114 # 08 Y:2006 08 2006 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR $91,228 $834,000 Not Implemented
IC0114 # 09 Y:2006 09 2006 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $10,414 $65,273 Implemented
IC0114 # 10 Y:2006 10 2006 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $2,000 $8,400 Implemented
IC0114 # 11 Y:2006 11 2006 INSTALL / REPAIR INSULATION ON STEAM LINES $4,400 $1,200 Implemented
IC0114 # 12 Y:2006 12 2006 REPAIR AND ELIMINATE STEAM LEAKS $2,000 $2,800 Implemented
IC0114 # 13 Y:2006 13 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,383 $9,400 Implemented
SU0231 # 01 Y:2006 01 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $11,122 $0 Not Implemented
SU0231 # 02 Y:2006 02 2006 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $4,090 $0 Implemented