IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,703

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SU0360 # 03 Y:2014 03 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $16,074 $3,375 Implemented
SU0360 # 04 Y:2014 04 2014 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $1,863 $3,874 Not Implemented
SU0360 # 05 Y:2014 05 2014 UPGRADE OBSOLETE EQUIPMENT $1,190 $3,188 Implemented
SU0360 # 06 Y:2014 06 2014 OPTIMIZE PLANT POWER FACTOR $28,089 $129,616 Not Implemented
SF0446 # 01 Y:2014 01 2014 REPAIR AND ELIMINATE STEAM LEAKS $3,935 $840 Implemented
SF0446 # 02 Y:2014 02 2014 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $477 $131 Implemented
SF0446 # 03 Y:2014 03 2014 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,568 $5,796 Implemented
SF0446 # 04 Y:2014 04 2014 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,787 $8,897 Implemented
SF0446 # 05 Y:2014 05 2014 REPLACE DC EQUIPMENT WITH AC EQUIPMENT $17,849 $58,975 Implemented
SF0446 # 06 Y:2014 06 2014 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $56,698 $210,000 Not Implemented
SF0446 # 07 Y:2014 07 2014 INSTALL OCCUPANCY SENSORS $7,640 $28,695 Implemented
SF0446 # 08 Y:2014 08 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,552 $15,048 Not Implemented
OR0628 # 01 Y:2014 01 2014 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $44,216 $17,353 Not Implemented
OR0628 # 02 Y:2014 02 2014 USE OPTIMUM THICKNESS INSULATION $3,869 $828 Not Implemented
OR0628 # 03 Y:2014 03 2014 PAY BILLS ON TIME TO AVOID LATE FEES $3,198 $0 Not Implemented
OR0628 # 04 Y:2014 04 2014 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $25,006 $4,810 Not Implemented
OR0628 # 05 Y:2014 05 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,875 $1,293 Not Implemented
OR0628 # 06 Y:2014 06 2014 UPGRADE CONVEYORS $20,000 $11,206 Not Implemented
OR0628 # 07 Y:2014 07 2014 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $9,718 $2,460 Implemented
OR0628 # 08 Y:2014 08 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $877 $500 Not Implemented
OR0628 # 09 Y:2014 09 2014 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $948 $676 Not Implemented
DL0126 # 01 Y:2014 01 2014 ADOPT IN-HOUSE MATERIAL GENERATION $283,400 $116,500 Implemented
DL0126 # 02 Y:2014 02 2014 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $19,000 $9,600 Not Implemented
DL0126 # 03 Y:2014 03 2014 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $17,400 $9,600 Not Implemented
DL0126 # 04 Y:2014 04 2014 ADJUST BURNERS FOR EFFICIENT OPERATION $15,000 $50,000 Not Implemented