Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,718
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0843 # 07 Y:2022 | 07 | 2022 | INSTALL OCCUPANCY SENSORS | $18 | $84 | Not Implemented |
AM0843 # 08 Y:2022 | 08 | 2022 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $180 | $160 | Not Implemented |
MA0837 # 01 Y:2022 | 01 | 2022 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $13,524 | $1,250 | Implemented |
MA0837 # 02 Y:2022 | 02 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,317 | $2,500 | Implemented |
MA0837 # 03 Y:2022 | 03 | 2022 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $10,507 | $46,265 | Not Implemented |
MA0837 # 04 Y:2022 | 04 | 2022 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,956 | $500 | Implemented |
MA0837 # 05 Y:2022 | 05 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,463 | $625 | Implemented |
MA0837 # 06 Y:2022 | 06 | 2022 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,316 | $600 | Implemented |
LS2214 # 01 Y:2022 | 01 | 2022 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $137 | $0 | Implemented |
LS2214 # 02 Y:2022 | 02 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,189 | $270 | Implemented |
LS2214 # 03 Y:2022 | 03 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $226 | $25 | Not Implemented |
LS2214 # 04 Y:2022 | 04 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $217 | $38 | Implemented |
LS2214 # 05 Y:2022 | 05 | 2022 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $53,187 | $50,000 | Implemented |
LS2214 # 06 Y:2022 | 06 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,374 | $1,394 | Not Implemented |
LS2214 # 07 Y:2022 | 07 | 2022 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $63 | $150 | Not Implemented |
TT0269 # 01 Y:2022 | 01 | 2022 | CHANGE ZONE REHEAT COILS TO VARIABLE AIR VOLUME BOXES | $24,682 | $2,000 | Not Implemented |
TT0269 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,069 | $25,000 | Not Implemented |
TT0269 # 03 Y:2022 | 03 | 2022 | OPTIMIZE PLANT POWER FACTOR | $6,223 | $27,500 | Not Implemented |
TT0269 # 04 Y:2022 | 04 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,847 | $3,500 | Not Implemented |
TT0269 # 05 Y:2022 | 05 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,648 | $2,500 | Not Implemented |
TT0269 # 06 Y:2022 | 06 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,911 | $11,000 | Not Implemented |
LS2213 # 01 Y:2022 | 01 | 2022 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $390 | $0 | Implemented |
LS2213 # 02 Y:2022 | 02 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $704 | $38 | Implemented |
LS2213 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,162 | $360 | Implemented |
LS2213 # 04 Y:2022 | 04 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $32,208 | $7,144 | Implemented |