Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,230
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0829 # 08 Y:2011 | 08 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $547 | $500 | Implemented |
UD0829 # 09 Y:2011 | 09 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,252 | $4,557 | Not Implemented |
UD0829 # 10 Y:2011 | 10 | 2011 | ISOLATE HOT OR COLD EQUIPMENT | $546 | $250 | Not Implemented |
UD0829 # 11 Y:2011 | 11 | 2011 | INSTALL FOSSIL FUEL MAKE-UP AIR UNIT | $2,189 | $9,500 | Not Implemented |
UD0829 # 12 Y:2011 | 12 | 2011 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,647 | $25 | Not Implemented |
UD0829 # 13 Y:2011 | 13 | 2011 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $688 | $1,500 | Not Implemented |
OR0566 # 01 Y:2011 | 01 | 2011 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,230 | $635 | Implemented |
OR0566 # 02 Y:2011 | 02 | 2011 | INSTALL OCCUPANCY SENSORS | $4,340 | $9,990 | Implemented |
OR0566 # 03 Y:2011 | 03 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,690 | $1,690 | Implemented |
OR0566 # 04 Y:2011 | 04 | 2011 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $8,620 | $37,500 | Not Implemented |
OR0566 # 05 Y:2011 | 05 | 2011 | USE SOLAR HEAT TO MAKE ELECTRICTY | $15,200 | $146,000 | Not Implemented |
SD0432 # 01 Y:2011 | 01 | 2011 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,239 | $0 | Implemented |
SD0432 # 02 Y:2011 | 02 | 2011 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $2,059 | $800 | Implemented |
SD0432 # 03 Y:2011 | 03 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $214 | $100 | Not Implemented |
SD0432 # 04 Y:2011 | 04 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,412 | $800 | Not Implemented |
SD0432 # 05 Y:2011 | 05 | 2011 | INSTALL OCCUPANCY SENSORS | $204 | $427 | Implemented |
SD0432 # 06 Y:2011 | 06 | 2011 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $3,408 | $8,000 | Not Implemented |
SD0432 # 07 Y:2011 | 07 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,373 | $8,285 | Not Implemented |
MA0667 # 01 Y:2011 | 01 | 2011 | REDUCE VENTILATION AIR | $45,912 | $17,705 | Not Implemented |
MA0667 # 02 Y:2011 | 02 | 2011 | IMPROVE COMBUSTION CONTROL CAPABILITY | $31,118 | $100,000 | Not Implemented |
MA0667 # 03 Y:2011 | 03 | 2011 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $11,694 | $10,590 | Implemented |
MA0667 # 04 Y:2011 | 04 | 2011 | REDUCE VENTILATION AIR | $8,118 | $0 | Implemented |
MA0667 # 05 Y:2011 | 05 | 2011 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $3,023 | $250 | Implemented |
MA0667 # 06 Y:2011 | 06 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,246 | $3,000 | Not Implemented |
MA0667 # 07 Y:2011 | 07 | 2011 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $5,047 | $17,500 | Not Implemented |