Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,718

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UU0199 # 03 Y:2022 03 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,884 $378 Not Implemented
UU0199 # 04 Y:2022 04 2022 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,264 $2,575 Implemented
UU0199 # 05 Y:2022 05 2022 REDUCE COMBUSTION AIR FLOW TO OPTIMUM $200 $564 Not Implemented
SF0582 # 01 Y:2022 01 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $21,960 $0 Implemented
SF0582 # 02 Y:2022 02 2022 MODIFY STARTUP/SHUTDOWN TIMES $7,144 $0 Implemented
SF0582 # 03 Y:2022 03 2022 INSTALL / REPAIR INSULATION ON STEAM LINES $29,881 $2,290 Implemented
SF0582 # 04 Y:2022 04 2022 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $10,294 $2,290 Implemented
SF0582 # 05 Y:2022 05 2022 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $22,836 $41,117 Implemented
SF0582 # 06 Y:2022 06 2022 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $24,257 $45,587 Implemented
SF0582 # 07 Y:2022 07 2022 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $8,094 $17,764 Implemented
SF0582 # 08 Y:2022 08 2022 INSULATE BARE EQUIPMENT $376 $961 Not Implemented
SF0582 # 09 Y:2022 09 2022 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $3,070 $11,782 Implemented
SF0582 # 10 Y:2022 10 2022 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,570 $11,279 Not Implemented
OK1068 # 01 Y:2022 01 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,103 $0 Implemented
OK1068 # 02 Y:2022 02 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,141 $1,208 Implemented
OK1068 # 03 Y:2022 03 2022 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER $5,553 $3,192 Implemented
OK1068 # 04 Y:2022 04 2022 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $3,561 $18,463 Not Implemented
OK1068 # 05 Y:2022 05 2022 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $830 $0 Not Implemented
OK1068 # 06 Y:2022 06 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,325 $5,412 Implemented
UL2202 # 01 Y:2022 01 2022 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $23,158 $0 Implemented
UL2202 # 02 Y:2022 02 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,861 $12,941 Implemented
UL2202 # 03 Y:2022 03 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,677 $0 Implemented
UL2202 # 04 Y:2022 04 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $649 $0 Not Implemented
UL2202 # 05 Y:2022 05 2022 OPTIMIZE PLANT POWER FACTOR $16,897 $12,250 Not Implemented
UL2202 # 06 Y:2022 06 2022 USE SOLAR HEAT TO MAKE ELECTRICTY $50,126 $1,220,427 Not Implemented