Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,640
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0613 # 01 Y:2001 | 01 | 2001 | INSTALL SET-BACK TIMERS | $10,756 | $1,026 | Not Implemented |
OK0613 # 02 Y:2001 | 02 | 2001 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,071 | $4,000 | Implemented |
OK0613 # 03 Y:2001 | 03 | 2001 | INSTALL / REPAIR INSULATION ON STEAM LINES | $456 | $2,600 | Implemented |
OK0613 # 04 Y:2001 | 04 | 2001 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,475 | $7,120 | Not Implemented |
OK0613 # 05 Y:2001 | 05 | 2001 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,508 | $6,000 | Not Implemented |
OK0613 # 06 Y:2001 | 06 | 2001 | RECOVER AND REUSE WASTE MATERIAL | $54,883 | $20,680 | Not Implemented |
OK0613 # 07 Y:2001 | 07 | 2001 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,400 | $572 | Not Implemented |
OK0613 # 08 Y:2001 | 08 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $304 | $125 | Not Implemented |
LE0108 # 01 Y:2001 | 01 | 2001 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $7,746 | $2,500 | Not Implemented |
LE0108 # 02 Y:2001 | 02 | 2001 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,248 | $0 | Implemented |
LE0108 # 03 Y:2001 | 03 | 2001 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $2,738 | $3,120 | Implemented |
LE0108 # 04 Y:2001 | 04 | 2001 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $315 | $500 | Implemented |
AS0297 # 01 Y:2001 | 01 | 2001 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $166,920 | $35,000 | n/a |
AS0297 # 02 Y:2001 | 02 | 2001 | INSTALL SKYLIGHTS | $1,527 | $3,086 | Not Implemented |
AS0297 # 03 Y:2001 | 03 | 2001 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $520 | $240 | Not Implemented |
AS0297 # 04 Y:2001 | 04 | 2001 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $25,657 | $90,000 | n/a |
AS0297 # 05 Y:2001 | 05 | 2001 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $3,360 | $60 | Not Implemented |
AS0297 # 06 Y:2001 | 06 | 2001 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $5,712 | $5,916 | Not Implemented |
OR0390 # 01 Y:2001 | 01 | 2001 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $79,800 | $30,700 | Implemented |
OR0390 # 02 Y:2001 | 02 | 2001 | OPTIMIZE PLANT POWER FACTOR | $2,467 | $2,100 | Not Implemented |
OR0390 # 03 Y:2001 | 03 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,749 | $1,700 | Implemented |
OR0390 # 04 Y:2001 | 04 | 2001 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,277 | $2,100 | Implemented |
OR0390 # 05 Y:2001 | 05 | 2001 | COMBINE UTILITY METERS | $1,062 | $3,925 | Not Implemented |
OR0389 # 01 Y:2001 | 01 | 2001 | MODIFY CURRENT INCENTIVE PROGRAM | $289,800 | $26,680 | Implemented |
OR0389 # 02 Y:2001 | 02 | 2001 | CHANGE METHOD OF DEIONIZED WATER PRODUCTION | $29,980 | $20,000 | Implemented |