IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,568

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0048 # 04 Y:1989 04 1989 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $135 $138 Not Implemented
OR0048 # 05 Y:1989 05 1989 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $1,545 $7,500 Implemented
OR0048 # 06 Y:1989 06 1989 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $10,327 $13,600 Not Implemented
OR0048 # 07 Y:1989 07 1989 OPTIMIZE PLANT POWER FACTOR $592 $1,500 Implemented
OR0043 # 05 Y:1988 05 1988 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $433 $908 Implemented
OR0043 # 06 Y:1988 06 1988 OPTIMIZE PLANT POWER FACTOR $2,458 $5,400 Implemented
OR0043 # 07 Y:1988 07 1988 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $5,196 $12,635 Not Implemented
OR0041 # 01 Y:1988 01 1988 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $527 $0 Not Implemented
OR0041 # 02 Y:1988 02 1988 USE MINIMUM STEAM OPERATING PRESSURE $254 $0 Implemented
OR0041 # 03 Y:1988 03 1988 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $949 $300 Implemented
OR0041 # 04 Y:1988 04 1988 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $941 $475 Not Implemented
OR0041 # 05 Y:1988 05 1988 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $158 $136 Not Implemented
OR0041 # 06 Y:1988 06 1988 INSTALL / REPAIR INSULATION ON STEAM LINES $2,075 $1,966 Not Implemented
OR0041 # 07 Y:1988 07 1988 INSULATE FEEDWATER TANK $94 $177 Not Implemented
OR0042 # 01 Y:1988 01 1988 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $2,776 $0 Implemented
OR0042 # 02 Y:1988 02 1988 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $22,164 $5,000 Implemented
OR0042 # 03 Y:1988 03 1988 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,349 $500 Not Implemented
OR0042 # 04 Y:1988 04 1988 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,087 $623 Implemented
OR0042 # 05 Y:1988 05 1988 OPTIMIZE PLANT POWER FACTOR $2,293 $4,800 Implemented
OR0042 # 06 Y:1988 06 1988 USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS $36,759 $0 Not Implemented
OR0043 # 01 Y:1988 01 1988 USE MINIMUM STEAM OPERATING PRESSURE $506 $0 Implemented
OR0043 # 02 Y:1988 02 1988 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $471 $258 Not Implemented
OR0043 # 03 Y:1988 03 1988 INSULATE BARE EQUIPMENT $1,171 $627 Implemented
OR0043 # 04 Y:1988 04 1988 INSTALL / REPAIR INSULATION ON STEAM LINES $1,477 $1,900 Implemented
OR0037 # 01 Y:1988 01 1988 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $6,463 $0 Not Implemented