IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,043

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0843 # 08 Y:2013 08 2013 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $1,735 $3,900 Not Implemented
OK0843 # 09 Y:2013 09 2013 INSTALL SET-BACK TIMERS $709 $1,288 Not Implemented
OK0843 # 10 Y:2013 10 2013 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $704 $280 Not Implemented
OK0843 # 11 Y:2013 11 2013 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $4,107 $3,900 Not Implemented
OK0843 # 12 Y:2013 12 2013 INSULATE BARE EQUIPMENT $263 $768 Not Implemented
OK0843 # 13 Y:2013 13 2013 OPTIMIZE PLANT POWER FACTOR $3,539 $11,638 Not Implemented
OK0844 # 01 Y:2013 01 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,922 $21,000 Implemented
OK0844 # 02 Y:2013 02 2013 OPTIMIZE PLANT POWER FACTOR $6,000 $32,130 Not Implemented
OK0844 # 03 Y:2013 03 2013 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $11,299 $76,750 Implemented
OK0844 # 04 Y:2013 04 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,154 $4,200 Implemented
OK0844 # 05 Y:2013 05 2013 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $6,800 $18,500 Not Implemented
OR0601 # 01 Y:2013 01 2013 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $4,114 $0 Implemented
OR0601 # 02 Y:2013 02 2013 IMPROVE COMBUSTION CONTROL CAPABILITY $10,408 $3,874 Not Implemented
OR0601 # 03 Y:2013 03 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,167 $2,000 Not Implemented
OR0601 # 04 Y:2013 04 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,338 $1,616 Not Implemented
OR0601 # 05 Y:2013 05 2013 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $51,858 $112,345 Not Implemented
OR0601 # 06 Y:2013 06 2013 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $6,546 $5,306 Implemented
OR0601 # 07 Y:2013 07 2013 ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION $9,479 $35,500 Not Implemented
OR0601 # 08 Y:2013 08 2013 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES $2,164 $8,104 Implemented
SU0337 # 01 Y:2013 01 2013 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $85 $0 Not Implemented
SU0337 # 02 Y:2013 02 2013 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,848 $517 Implemented
SU0337 # 03 Y:2013 03 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,655 $2,760 Implemented
SU0337 # 04 Y:2013 04 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $469 $346 Implemented
SU0337 # 05 Y:2013 05 2013 INSTALL / REPAIR INSULATION ON STEAM LINES $693 $895 Implemented
SU0337 # 06 Y:2013 06 2013 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $290 $596 Not Implemented