IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,703

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0443 # 06 Y:2014 06 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,897 $24,840 Not Implemented
SF0443 # 07 Y:2014 07 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,886 $16,744 Not Implemented
SF0443 # 08 Y:2014 08 2014 INSULATE BARE EQUIPMENT $9,060 $45,537 Not Implemented
SF0443 # 09 Y:2014 09 2014 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $63,378 $31,000 Implemented
SF0443 # 10 Y:2014 10 2014 MINIMIZE CONTAMINATION OF WATER BEFORE TREATMENT $11,793 $50,140 Not Implemented
SF0443 # 11 Y:2014 11 2014 USE SOLAR HEAT TO MAKE ELECTRICTY $67,869 $444,663 Not Implemented
SU0357 # 01 Y:2014 01 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $509 $0 Not Implemented
SU0357 # 02 Y:2014 02 2014 INSTALL OCCUPANCY SENSORS $1,140 $521 Not Implemented
SU0357 # 03 Y:2014 03 2014 DISCONNECT BALLASTS $96 $0 Implemented
SU0357 # 04 Y:2014 04 2014 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,080 $749 Not Implemented
SU0357 # 05 Y:2014 05 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,211 $1,388 Implemented
SU0357 # 06 Y:2014 06 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $595 $532 Implemented
SU0357 # 07 Y:2014 07 2014 ELIMINATE/REDUCE AN OPERATION $1,151 $1,668 Not Implemented
AM0650 # 01 Y:2014 01 2014 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $17,640 $0 Implemented
AM0650 # 02 Y:2014 02 2014 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES $31,250 $10,000 Implemented
AM0650 # 03 Y:2014 03 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,060 $1,200 Implemented
AM0650 # 04 Y:2014 04 2014 OPTIMIZE PLANT POWER FACTOR $2,335 $6,805 Not Implemented
AM0650 # 05 Y:2014 05 2014 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $2,190 $4,080 Implemented
AM0650 # 06 Y:2014 06 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,050 $605 Implemented
AM0650 # 07 Y:2014 07 2014 INSTALL OCCUPANCY SENSORS $540 $550 Implemented
AM0650 # 08 Y:2014 08 2014 USE SYNTHETIC LUBRICANT $432 $0 Not Implemented
AM0650 # 09 Y:2014 09 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $425 $20 Not Implemented
IP0021 # 01 Y:2014 01 2014 APPLY FOR INVESTMENT INCENTIVES $4,267 $0 Not Implemented
IP0021 # 02 Y:2014 02 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,655 $0 Implemented
IP0021 # 03 Y:2014 03 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $513 $0 Implemented