IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,533

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WV0311 # 12 Y:2005 12 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $480 $158 Implemented
WV0310 # 01 Y:2005 01 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,059 $8,260 Not Implemented
WV0310 # 02 Y:2005 02 2005 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $6,573 $8,352 Not Implemented
WV0310 # 03 Y:2005 03 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,268 $0 Not Implemented
WV0310 # 04 Y:2005 04 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,968 $11,900 Not Implemented
WV0310 # 05 Y:2005 05 2005 OPTIMIZE PLANT POWER FACTOR $2,190 $820 Not Implemented
WV0310 # 06 Y:2005 06 2005 DEVELOP A REPAIR/REPLACE POLICY $1,229 $304 Not Implemented
WV0310 # 07 Y:2005 07 2005 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $1,763 $336 Not Implemented
WV0310 # 08 Y:2005 08 2005 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,536 $870 Not Implemented
WV0310 # 09 Y:2005 09 2005 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $951 $238 Not Implemented
WV0310 # 10 Y:2005 10 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $943 $24 Not Implemented
WV0310 # 11 Y:2005 11 2005 INSTALL OCCUPANCY SENSORS $921 $2,268 Not Implemented
WV0310 # 12 Y:2005 12 2005 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $560 $145 Not Implemented
WV0310 # 13 Y:2005 13 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $539 $132 Not Implemented
GT0799 # 01 Y:2005 01 2005 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $6,890 $450 Not Implemented
GT0799 # 02 Y:2005 02 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,582 $3,682 Implemented
GT0799 # 03 Y:2005 03 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,040 $280,000 Not Implemented
GT0799 # 04 Y:2005 04 2005 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $4,608 $12,000 Not Implemented
GT0799 # 05 Y:2005 05 2005 RECOVER WASTE HEAT FROM EQUIPMENT $29,409 $260,000 Not Implemented
GT0799 # 06 Y:2005 06 2005 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $16,500 $60,000 Implemented
LL0219 # 01 Y:2005 01 2005 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $49,904 $26,850 Implemented
LL0219 # 02 Y:2005 02 2005 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $38,931 $18,717 Implemented
LL0219 # 03 Y:2005 03 2005 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $18,345 $4,495 Not Implemented
LL0219 # 04 Y:2005 04 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $10,142 $60 Implemented
LL0219 # 05 Y:2005 05 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,865 $3,360 Implemented