Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,520
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DS0138 # 06 Y:1999 | 06 | 1999 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,688 | $0 | Not Implemented |
DS0138 # 07 Y:1999 | 07 | 1999 | INCREASE USE OF AUTOMATION | $96,760 | $65,000 | Implemented |
DS0139 # 01 Y:1999 | 01 | 1999 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $560 | $270 | Implemented |
DS0139 # 02 Y:1999 | 02 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $882 | $500 | Implemented |
DS0139 # 03 Y:1999 | 03 | 1999 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,693 | $391 | Implemented |
DS0139 # 04 Y:1999 | 04 | 1999 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $595 | $800 | Not Implemented |
DS0139 # 05 Y:1999 | 05 | 1999 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $1,515 | $3,300 | Not Implemented |
DS0139 # 06 Y:1999 | 06 | 1999 | INSTALL SHELVES / RACKS TO UTILIZE UNUSED SPACE | $2,633 | $7,000 | Implemented |
MA0437 # 01 Y:1999 | 01 | 1999 | INSTALL / REPAIR INSULATION ON STEAM LINES | $17,316 | $3,000 | Not Implemented |
MA0437 # 02 Y:1999 | 02 | 1999 | INSTALL / REPAIR INSULATION ON STEAM LINES | $8,292 | $1,892 | Not Implemented |
MA0437 # 03 Y:1999 | 03 | 1999 | UPGRADE CONTROLS ON COMPRESSORS | $6,214 | $400 | Implemented |
MA0437 # 04 Y:1999 | 04 | 1999 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $2,225 | $300 | Implemented |
MA0437 # 05 Y:1999 | 05 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,451 | $2,445 | Implemented |
MA0437 # 06 Y:1999 | 06 | 1999 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $774 | $0 | Implemented |
NC0161 # 01 Y:1999 | 01 | 1999 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,160 | $500 | Not Implemented |
NC0161 # 02 Y:1999 | 02 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,328 | $20 | Not Implemented |
NC0161 # 03 Y:1999 | 03 | 1999 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,140 | $1,650 | Implemented |
NC0161 # 04 Y:1999 | 04 | 1999 | BURN WASTE TO PRODUCE STEAM TO DRIVE A STEAM TURBINE GENERATOR SET AND USE STEAM EXHAUST FOR HEAT | $160,533 | $279,000 | Not Implemented |
NC0161 # 05 Y:1999 | 05 | 1999 | BURN WASTE PAPER FOR HEAT | $281 | $0 | Not Implemented |
OD0135 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $331 | $773 | Not Implemented |
OD0135 # 02 Y:1999 | 02 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $849 | $800 | Implemented |
OD0135 # 03 Y:1999 | 03 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $79 | $20 | Not Implemented |
OD0135 # 04 Y:1999 | 04 | 1999 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $413 | $1,870 | Not Implemented |
NC0163 # 01 Y:1999 | 01 | 1999 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $11,222 | $17,000 | Implemented |
NC0163 # 02 Y:1999 | 02 | 1999 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,614 | $1,600 | Implemented |