Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,602
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0516 # 06 Y:2006 | 06 | 2006 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $430 | $0 | Implemented |
TA0119 # 01 Y:2006 | 01 | 2006 | OPTIMIZE PLANT POWER FACTOR | $14,150 | $25,000 | Implemented |
TA0119 # 02 Y:2006 | 02 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,785 | $385 | Implemented |
TA0119 # 03 Y:2006 | 03 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $480 | $0 | Implemented |
TA0119 # 04 Y:2006 | 04 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $370 | $370 | Implemented |
TA0119 # 05 Y:2006 | 05 | 2006 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $60 | $0 | Implemented |
TA0118 # 01 Y:2006 | 01 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,339 | $2,016 | Implemented |
TA0118 # 02 Y:2006 | 02 | 2006 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,842 | $2,000 | Implemented |
TA0118 # 03 Y:2006 | 03 | 2006 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $141 | $141 | Not Implemented |
TA0118 # 04 Y:2006 | 04 | 2006 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,049 | $90 | Implemented |
TA0118 # 05 Y:2006 | 05 | 2006 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $520 | $0 | Implemented |
TA0118 # 06 Y:2006 | 06 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $350 | $0 | Implemented |
TA0117 # 01 Y:2006 | 01 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,020 | $7,980 | Implemented |
TA0117 # 02 Y:2006 | 02 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,208 | $5,065 | Implemented |
TA0117 # 03 Y:2006 | 03 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,925 | $9 | Implemented |
TA0117 # 04 Y:2006 | 04 | 2006 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $478 | $0 | Implemented |
TA0117 # 05 Y:2006 | 05 | 2006 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,356 | $0 | Implemented |
TA0117 # 06 Y:2006 | 06 | 2006 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $45,290 | $22,980 | Not Implemented |
AM0515 # 01 Y:2006 | 01 | 2006 | BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT | $1,467,000 | $250,000 | Not Implemented |
AM0515 # 02 Y:2006 | 02 | 2006 | STORE HEATED/ COOLED WATER FOR USE DURING PEAK DEMAND PERIODS | $897,000 | $3,260,000 | Not Implemented |
AM0515 # 03 Y:2006 | 03 | 2006 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $66,000 | $65,000 | Implemented |
AM0515 # 04 Y:2006 | 04 | 2006 | INSTALL EQUIPMENT TO UTILIZE WASTE FUEL | $29,840 | $13,000 | Not Implemented |
AM0515 # 05 Y:2006 | 05 | 2006 | MINIMIZE WATER USAGE | $24,580 | $15,000 | Not Implemented |
AM0515 # 06 Y:2006 | 06 | 2006 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $16,500 | $6,700 | Implemented |
AM0515 # 07 Y:2006 | 07 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $9,580 | $27,400 | Implemented |