Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,713
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0597 # 04 Y:2023 | 04 | 2023 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $6,142 | $22,000 | Implemented |
UF0597 # 05 Y:2023 | 05 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $3,959 | $11,134 | Implemented |
UF0597 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,382 | $13,706 | Implemented |
UF0597 # 07 Y:2023 | 07 | 2023 | INSTALL OCCUPANCY SENSORS | $1,699 | $4,994 | Implemented |
UF0597 # 08 Y:2023 | 08 | 2023 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $51,744 | $18,218 | Implemented |
UF0597 # 09 Y:2023 | 09 | 2023 | IMPROVE SPACE COMFORT CONDITIONING | $35,500 | $4,261 | Implemented |
UF0596 # 01 Y:2023 | 01 | 2023 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $1,546,439 | $3,990,000 | Not Implemented |
UF0596 # 02 Y:2023 | 02 | 2023 | INSTALL SUB-METERING EQUIPMENT | $266,539 | $15,232 | Implemented |
UF0596 # 03 Y:2023 | 03 | 2023 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $232,670 | $300,000 | Implemented |
UF0596 # 04 Y:2023 | 04 | 2023 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $213,087 | $0 | Implemented |
UF0596 # 05 Y:2023 | 05 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $145,162 | $141,225 | Implemented |
UF0596 # 06 Y:2023 | 06 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $50,904 | $49,563 | Implemented |
UF0596 # 07 Y:2023 | 07 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $47,000 | $171,903 | Implemented |
UF0596 # 08 Y:2023 | 08 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $27,499 | $1,399 | Implemented |
UF0596 # 09 Y:2023 | 09 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $12,289 | $25,440 | Implemented |
UF0596 # 10 Y:2023 | 10 | 2023 | IMPROVE SPACE COMFORT CONDITIONING | $26,447 | $4,768 | Implemented |
UF0596 # 11 Y:2023 | 11 | 2023 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $3,156 | $2,352 | Implemented |
UF0595 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $95,368 | $289,896 | Not Implemented |
UF0595 # 02 Y:2023 | 02 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $39,683 | $20,785 | Implemented |
UF0595 # 03 Y:2023 | 03 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $18,931 | $25,400 | Implemented |
UF0595 # 04 Y:2023 | 04 | 2023 | USER BATTERY STORAGE FOR POWER QUALITY ISSUES | $6,261 | $20,000 | Not Implemented |
UF0595 # 05 Y:2023 | 05 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,458 | $356 | Implemented |
UF0595 # 06 Y:2023 | 06 | 2023 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $2,957 | $3,276 | Implemented |
UF0595 # 07 Y:2023 | 07 | 2023 | INSTALL SUB-METERING EQUIPMENT | $1,589 | $4,340 | Implemented |
UF0595 # 08 Y:2023 | 08 | 2023 | MINIMIZE CONDENSER COOLING WATER TEMPERATURE | $1,317 | $5,838 | Implemented |