Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,990
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0790 # 10 Y:2009 | 10 | 2009 | UPGRADE CONTROLS ON COMPRESSORS | $3,561 | $200 | Implemented |
UD0790 # 11 Y:2009 | 11 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,374 | $2,000 | Implemented |
UD0790 # 12 Y:2009 | 12 | 2009 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $2,006 | $0 | Implemented |
UD0790 # 13 Y:2009 | 13 | 2009 | ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF | $1,658 | $1,250 | Not Implemented |
UD0790 # 14 Y:2009 | 14 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $376 | $1,000 | Implemented |
UM0347 # 01 Y:2008 | 01 | 2008 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $9,638 | $8,898 | Not Implemented |
UM0347 # 02 Y:2008 | 02 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,545 | $6,240 | Not Implemented |
UM0347 # 03 Y:2008 | 03 | 2008 | COVER OPEN TANKS | $2,233 | $1,046 | Not Implemented |
UM0347 # 04 Y:2008 | 04 | 2008 | INSTALL OCCUPANCY SENSORS | $1,503 | $500 | Not Implemented |
UM0347 # 05 Y:2008 | 05 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $452 | $422 | Not Implemented |
UM0347 # 06 Y:2008 | 06 | 2008 | INSTALL AUTOMATIC STACK DAMPER | $29,890 | $8,100 | Not Implemented |
WV0385 # 01 Y:2008 | 01 | 2008 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $40,090 | $4,000 | Not Implemented |
WV0385 # 02 Y:2008 | 02 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $34,198 | $81,425 | Implemented |
WV0385 # 03 Y:2008 | 03 | 2008 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $14,879 | $21,600 | Not Implemented |
WV0385 # 04 Y:2008 | 04 | 2008 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $14,783 | $5,000 | Not Implemented |
WV0385 # 05 Y:2008 | 05 | 2008 | STANDARDIZE MOTOR INVENTORY | $6,638 | $763 | Implemented |
WV0385 # 06 Y:2008 | 06 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,599 | $548 | Implemented |
WV0385 # 07 Y:2008 | 07 | 2008 | INSULATE BARE EQUIPMENT | $3,100 | $140 | Implemented |
WV0385 # 08 Y:2008 | 08 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,980 | $0 | Implemented |
WV0385 # 09 Y:2008 | 09 | 2008 | IMPROVE LUBRICATION PRACTICES | $2,864 | $2,950 | Not Implemented |
WV0385 # 10 Y:2008 | 10 | 2008 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,986 | $792 | Implemented |
WV0385 # 11 Y:2008 | 11 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,425 | $4,393 | Implemented |
WV0385 # 12 Y:2008 | 12 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,167 | $925 | Not Implemented |
WV0385 # 13 Y:2008 | 13 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $527 | $100 | Implemented |
WV0385 # 14 Y:2008 | 14 | 2008 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $324 | $50 | Not Implemented |