IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

5,394

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SD0334 # 09 Y:2004 09 2004 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $4,200 $10,000 Not Implemented
SF0277 # 01 Y:2004 01 2004 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $38,710 $0 Implemented
SF0277 # 02 Y:2004 02 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,221 $0 Implemented
SF0277 # 03 Y:2004 03 2004 TURN OFF EQUIPMENT WHEN NOT IN USE $2,460 $720 Implemented
SF0277 # 04 Y:2004 04 2004 TURN OFF EQUIPMENT WHEN NOT IN USE $954 $240 Not Implemented
SF0277 # 05 Y:2004 05 2004 TURN OFF EQUIPMENT WHEN NOT IN USE $784 $240 Implemented
SF0277 # 06 Y:2004 06 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $16,226 $5,882 Not Implemented
SF0277 # 07 Y:2004 07 2004 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $13,431 $16,011 Not Implemented
SF0277 # 08 Y:2004 08 2004 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $10,600 $13,520 Implemented
SF0277 # 09 Y:2004 09 2004 INSTALL OCCUPANCY SENSORS $1,907 $3,072 Not Implemented
SF0277 # 10 Y:2004 10 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $21,365 $41,948 Not Implemented
SF0277 # 11 Y:2004 11 2004 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $10,871 $29,053 Not Implemented
SF0277 # 12 Y:2004 12 2004 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,600 $32,344 Not Implemented
SF0277 # 13 Y:2004 13 2004 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $5,568 $18,000 Not Implemented
SF0277 # 14 Y:2004 14 2004 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE $7,239 $0 Not Implemented
SF0277 # 15 Y:2004 15 2004 CHANGE OPERATING CONDITIONS $5,549 $0 Not Implemented
SF0277 # 16 Y:2004 16 2004 OPTIMIZE PLANT POWER FACTOR $3,454 $5,667 Not Implemented
SF0279 # 01 Y:2004 01 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $699 $0 Implemented
SF0279 # 02 Y:2004 02 2004 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $11,368 $11,810 Not Implemented
SF0279 # 03 Y:2004 03 2004 INSTALL OCCUPANCY SENSORS $1,168 $1,200 Not Implemented
SF0279 # 04 Y:2004 04 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,520 $13,375 Implemented
SF0279 # 05 Y:2004 05 2004 OPTIMIZE PLANT POWER FACTOR $1,079 $1,376 Not Implemented
CO0540 # 01 Y:2004 01 2004 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $6,340 $8,790 Implemented
CO0540 # 02 Y:2004 02 2004 INSULATE BARE EQUIPMENT $5,600 $18,700 Not Implemented
CO0540 # 03 Y:2004 03 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,710 $200 Implemented