Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,708
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0229 # 03 Y:2002 | 03 | 2002 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $9,218 | $15,374 | Not Implemented |
LM0025 # 01 Y:2002 | 01 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,567 | $3,850 | Not Implemented |
LM0025 # 02 Y:2002 | 02 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,580 | $350 | Implemented |
LM0025 # 03 Y:2002 | 03 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,564 | $456 | Not Implemented |
LM0025 # 04 Y:2002 | 04 | 2002 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,122 | $3,375 | Not Implemented |
LM0025 # 05 Y:2002 | 05 | 2002 | SCHEDULE DELIVERIES ACCORDING TO DEMAND | $63,600 | $15,000 | Implemented |
LM0025 # 06 Y:2002 | 06 | 2002 | DEVELOP STANDARD OPERATING PROCEDURES | $31,500 | $9,240 | Implemented |
BD0201 # 01 Y:2002 | 01 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,916 | $9,150 | Not Implemented |
BD0201 # 02 Y:2002 | 02 | 2002 | INSTALL AUTOMATIC STACK DAMPER | $4,088 | $15,000 | Not Implemented |
BD0201 # 03 Y:2002 | 03 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,525 | $1,000 | Implemented |
BD0201 # 04 Y:2002 | 04 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,064 | $140 | Not Implemented |
BD0201 # 05 Y:2002 | 05 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $917 | $1,000 | Not Implemented |
BD0201 # 06 Y:2002 | 06 | 2002 | INSTALL OCCUPANCY SENSORS | $690 | $900 | Not Implemented |
BD0201 # 07 Y:2002 | 07 | 2002 | DISCONNECT BALLASTS | $653 | $240 | Implemented |
BD0201 # 08 Y:2002 | 08 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $368 | $323 | Not Implemented |
BD0201 # 09 Y:2002 | 09 | 2002 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $2,449 | $11,500 | Not Implemented |
BD0201 # 10 Y:2002 | 10 | 2002 | INCREASE USE OF AUTOMATION | $22,464 | $45,000 | Not Implemented |
BD0201 # 11 Y:2002 | 11 | 2002 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $620 | $100 | Implemented |
AM0407 # 01 Y:2002 | 01 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,330 | $300 | Implemented |
AM0407 # 02 Y:2002 | 02 | 2002 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $920 | $699 | Not Implemented |
AM0407 # 03 Y:2002 | 03 | 2002 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $690 | $210 | Not Implemented |
AM0407 # 04 Y:2002 | 04 | 2002 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $190 | $0 | Implemented |
AM0407 # 05 Y:2002 | 05 | 2002 | REUSE RAGS UNTIL COMPLETELY SOILED | $180 | $0 | Implemented |
MA0505 # 01 Y:2002 | 01 | 2002 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $55,391 | $74,250 | Not Implemented |
MA0505 # 02 Y:2002 | 02 | 2002 | REPLACE TREATED WATER WITH WELL / SURFACE WATER | $37,920 | $18,500 | Not Implemented |