Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,333
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0158 # 01 Y:2000 | 01 | 2000 | REPAIR OR REPLACE STEAM TRAPS | $67,296 | $2,200 | Implemented |
UM0158 # 02 Y:2000 | 02 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $6,190 | $1,400 | Not Implemented |
UM0158 # 03 Y:2000 | 03 | 2000 | INCREASE AMOUNT OF CONDENSATE RETURNED | $138,702 | $86,970 | Implemented |
UM0158 # 04 Y:2000 | 04 | 2000 | REDUCE EXCESSIVE BOILER BLOWDOWN | $11,891 | $9,860 | Not Implemented |
UM0158 # 05 Y:2000 | 05 | 2000 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $106,009 | $100,000 | Not Implemented |
UM0158 # 06 Y:2000 | 06 | 2000 | REDUCE FLUID FLOW RATES | $40,377 | $1,000 | Not Implemented |
UM0158 # 07 Y:2000 | 07 | 2000 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $364,003 | $3,000,000 | Not Implemented |
UM0157 # 01 Y:2000 | 01 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,161 | $150 | Implemented |
UM0157 # 02 Y:2000 | 02 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $746 | $500 | Implemented |
UM0157 # 03 Y:2000 | 03 | 2000 | REDUCE EXCESSIVE BOILER BLOWDOWN | $1,224 | $4,430 | Implemented |
UM0157 # 04 Y:2000 | 04 | 2000 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $8,000 | $400 | Not Implemented |
UM0157 # 05 Y:2000 | 05 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $1,296 | $738 | Implemented |
AM0367 # 01 Y:2000 | 01 | 2000 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $3,240 | $565 | Implemented |
AM0367 # 02 Y:2000 | 02 | 2000 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,560 | $0 | Implemented |
AM0367 # 03 Y:2000 | 03 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,090 | $500 | Implemented |
AM0367 # 04 Y:2000 | 04 | 2000 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $560 | $0 | Implemented |
AM0367 # 05 Y:2000 | 05 | 2000 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $505 | $290 | Implemented |
AM0367 # 06 Y:2000 | 06 | 2000 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $355 | $0 | Implemented |
AM0367 # 07 Y:2000 | 07 | 2000 | PAY BILLS ON TIME TO AVOID LATE FEES | $234 | $0 | Implemented |
AM0367 # 08 Y:2000 | 08 | 2000 | USE SYNTHETIC LUBRICANT | $130 | $0 | Implemented |
GT0683 # 01 Y:2000 | 01 | 2000 | COMBINE UTILITY METERS | $14,609 | $0 | Not Implemented |
GT0683 # 02 Y:2000 | 02 | 2000 | RECOVER WASTE HEAT FROM EQUIPMENT | $180,287 | $358,400 | Not Implemented |
GT0683 # 03 Y:2000 | 03 | 2000 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,689 | $2,080 | Not Implemented |
GT0683 # 04 Y:2000 | 04 | 2000 | INSTALL SYSTEM TO COLLECT SCRAP | $59,893 | $12,000 | Not Implemented |
GT0683 # 05 Y:2000 | 05 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,590 | $108,696 | Not Implemented |