Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
85
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0477 # 06 Y:1997 | 06 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $350 | $130 | Implemented |
KU0477 # 05 Y:1997 | 05 | 1997 | RECOVER WASTE HEAT FROM EQUIPMENT | $580 | $140 | Implemented |
KU0477 # 04 Y:1997 | 04 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $590 | $1,450 | Implemented |
KU0477 # 03 Y:1997 | 03 | 1997 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $640 | $1,000 | Implemented |
KU0477 # 02 Y:1997 | 02 | 1997 | INSTALL OCCUPANCY SENSORS | $2,980 | $1,600 | Implemented |
KU0477 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,340 | $18,090 | Implemented |
KU0477 # 07 Y:1997 | 07 | 1997 | USE SYNTHETIC LUBRICANT | $340 | $1,100 | Implemented |
KU0477 # 08 Y:1997 | 08 | 1997 | USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES | $1,330 | $1,050 | Not Implemented |
OK0528 # 05 Y:1997 | 05 | 1997 | USE OPTIMUM THICKNESS INSULATION | $747 | $166 | Implemented |
OK0528 # 06 Y:1997 | 06 | 1997 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $6,149 | $12,500 | Not Implemented |
OK0528 # 04 Y:1997 | 04 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $962 | $114 | Implemented |
OK0528 # 03 Y:1997 | 03 | 1997 | USE WASTE HEAT FROM HOT FLUE GASES TO GENERATE STEAM | $3,099 | $4,655 | Not Implemented |
OK0528 # 02 Y:1997 | 02 | 1997 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $6,011 | $3,500 | Implemented |
OK0528 # 01 Y:1997 | 01 | 1997 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $17,998 | $48,754 | Implemented |
OK0528 # 07 Y:1997 | 07 | 1997 | MOVE PRODUCT USING MECHANICAL MEANS | $39,936 | $28,000 | Not Implemented |
KU0476 # 09 Y:1997 | 09 | 1997 | RECYCLE CASTING SAND | $4,050 | $0 | Not Implemented |
KU0476 # 11 Y:1997 | 11 | 1997 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $7,620 | $0 | Implemented |
KU0476 # 10 Y:1997 | 10 | 1997 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $3,340 | $300 | Implemented |
KU0476 # 01 Y:1997 | 01 | 1997 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $13,340 | $0 | Implemented |
KU0476 # 08 Y:1997 | 08 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $180 | $270 | Implemented |
KU0476 # 07 Y:1997 | 07 | 1997 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $370 | $810 | Not Implemented |
KU0476 # 06 Y:1997 | 06 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $490 | $780 | Not Implemented |
KU0476 # 05 Y:1997 | 05 | 1997 | INSTALL OCCUPANCY SENSORS | $780 | $1,400 | Not Implemented |
KU0476 # 04 Y:1997 | 04 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,010 | $230 | Implemented |
KU0476 # 03 Y:1997 | 03 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,360 | $5,470 | Implemented |