Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,443
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0441 # 09 Y:2009 | 09 | 2009 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $49,777 | $70,000 | Not Implemented |
IA0441 # 10 Y:2009 | 10 | 2009 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $25,097 | $27,000 | Implemented |
IA0441 # 11 Y:2009 | 11 | 2009 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,289 | $16,600 | Implemented |
IA0438 # 01 Y:2009 | 01 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,772 | $59,001 | Implemented |
IA0438 # 02 Y:2009 | 02 | 2009 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $259 | $50 | Implemented |
IA0438 # 03 Y:2009 | 03 | 2009 | DISCONNECT BALLASTS | $330 | $250 | Implemented |
IA0438 # 04 Y:2009 | 04 | 2009 | INSTALL OCCUPANCY SENSORS | $799 | $462 | Not Implemented |
IA0438 # 05 Y:2009 | 05 | 2009 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $346 | $515 | Not Implemented |
IA0438 # 06 Y:2009 | 06 | 2009 | ADD AREA LIGHTING SWITCHES | $7,861 | $2,200 | Implemented |
IA0438 # 07 Y:2009 | 07 | 2009 | USE RE-USABLE FILTERS | $15,000 | $7,540 | Not Implemented |
IA0438 # 08 Y:2009 | 08 | 2009 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $10,670 | $2,000 | Implemented |
IA0424 # 01 Y:2008 | 01 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $333 | $13 | Implemented |
IA0424 # 02 Y:2008 | 02 | 2008 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,811 | $134 | Not Implemented |
IA0424 # 03 Y:2008 | 03 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,627 | $3,004 | Implemented |
IA0424 # 04 Y:2008 | 04 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,324 | $4,198 | Not Implemented |
IA0424 # 05 Y:2008 | 05 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,992 | $7,650 | Implemented |
IA0424 # 06 Y:2008 | 06 | 2008 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $801 | $780 | Implemented |
CO0606 # 01 Y:2007 | 01 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,880 | $620 | Implemented |
CO0606 # 02 Y:2007 | 02 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,100 | $60 | Implemented |
CO0606 # 03 Y:2007 | 03 | 2007 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,150 | $2,680 | Implemented |
CO0606 # 04 Y:2007 | 04 | 2007 | USE EVAPORATION TO CONCENTRATE MATERIAL | $1,060 | $3,000 | Not Implemented |
CO0606 # 05 Y:2007 | 05 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,630 | $69,110 | Implemented |
CO0606 # 06 Y:2007 | 06 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,790 | $10,000 | Implemented |
CO0606 # 07 Y:2007 | 07 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,080 | $13,670 | Implemented |
CO0606 # 08 Y:2007 | 08 | 2007 | INSTALL OCCUPANCY SENSORS | $1,890 | $9,180 | Implemented |